Safety Due to fluid contents being under pressu re eye protection is recommended for operators. Refer to MSDS sheets on fluid be ing dispensed for and other precautions. A grounding wire should be connected to the st ain…

100%1 / 8
FCS300-R-2LT-H (163-03534)
Complete Manual Conformal Coating System
Thank you for purchasing the coating system from PVA. Before attempting to
operate the unit, we recommend that you take a few minutes and read the following
operation and setup manual. This will assist in familiarizing you with the product and
ensure a successful installation.
As always, if any questions or problems arise, do not hesitate to contact PVA’s
Service Department for support. This department can be reached at PVA headquarters by
telephone at (518) 371-2684.
Again, thank you for your purchase, and we look forward to assisting you in the
future as you continue to improve your dispensing processes.
Theory of Operation
This manual conformal coating system is designed to allow operators to utilize
PVA’s high quality spray valve technology in a hand held applications. The system utilizes
a small 2-Liter bottle pressure tank to hold fluid that can be placed on a bench top or on the
floor to feed the valve. An FCS300-R spray valve is mounted to a pneumatic trigger handle
which allows the operator to easily articulate the valve over the part and utilize the trigger
activate the spray.
When the trigger is depressed, the valve will activate to begin fluid flow and
simultaneously turn on the atomizing air in order to spray the coating to the substrate. As
soon as the trigger is released, the flow of fluid and atomizing air will cease.
The system is designed with Stainless Steel components and a UV safe, Teflon
fluid line to provide the greatest level of compatibility with a wide variety of fluids.
Chemistries that can be used in this system include, but are not limited to Acrylics,
Urethanes, Silicones, Epoxies, Solvent basted coatings, etc.
All wetted components of the system include:
- 303, 304 stainless steel
- Teflon
- Kalrez
Safety
Due to fluid contents being under pressure eye protection is recommended for
operators. Refer to MSDS sheets on fluid being dispensed for and other precautions.
A grounding wire should be connected to the stainless steel pressure tank to remove esd.
Setup
Refer to assembly drawing 163-03534 for part reference numbers.
1. Connect the system as outlined in the assembly drawing. Being sure the fluid lines
are tightly crimped in the fluid compression fittings and air lines are secure in the
quick connect fittings.
2. Connect main air to the quick connect air fitting of the fluid tank (9) and fitting
(1) of the main air regulator feeding the valve handle.
System Operation
Initial Startup
1. First, be sure the quick air shutoff valve (red handle) of the pressure tank (9) is
turned to the Ext. position so that no air pressure is being supplied to the tank.
Note: Be sure the pressure gauge reads zero before proceeding to the next step.
2. To load fluid into the system, evenly unthread the three handles on top of the tank
until they are loose from the tank top.
Note: The handles will remain connected to the tank lid.
3. Slowly remove the tank lid assembly from the tank body.
4. Place a full bottle of fluid inside the center of the tank with the cap removed.
5. Replace the lid assembly onto the tank, being sure the dip tube that is connected
to the center of the lid inserts into the fluid bottle.
6. Tighten the three handles down evenly for air tight seal.
7. Adjust the pressure on the air regulator (2) feeding the valve handle to 80 psi.
8. Depress the trigger on the handle (15) to cycle the valve open and closed. You
should hear the solenoid actuating inside the handle and will be able to see the
center needle of the spray valve (13) moving back and forth.
9. Adjust the pressure on the atomizing air regulator (20) between 2-3psi for startup.
Note: This pressure will only activate when the trigger of the handle (15) is
pressed.
10. To begin flow of fluid to the valve, open the quick air shutoff valve (red handle)
on the pressure tank (9) and adjust the air regulator to achieve the desired fluid
flow rate.
Note: To begin, start off with a low pressure (5psi.) and increase as necessary.
11. Hold the valve (13) and trigger handle assembly (15) aiming it in a direction
where the fluid can be purged.
12. Depress the trigger of the handle assembly (15) to begin fluid flow. Once fluid
begins to spray from the air cap of the valve (13) continue spraying until all air is
removed from the fluid lines.
13. Adjust the settings and begin to coat.
Adjusting Settings
There are several settings that can be adjusted to fine tune the spray pattern. These
settings are determined by the fluid viscosity, desired pattern width, and coating
thickness.
1. Based on the viscosity, the air pressure regulator of the fluid tank (9) should be
adjusted to supply an adequate flow of fluid to the spray valve.
2. The stroke adjustment of the spray valve (13) should be used to fine tune the fluid
flow rate from the valve.
Note: Refer to the valve manual for further instructions.
3. Adjust the atomizing air regulator (20) to control the volume of air that is used to
break up the fluid and transfer it to the part.
Note: Increasing atomizing air pressure will increase your spray pattern width and
decrease the coating thickness.
Material Change Over
1. First, remove air pressure from the fluid tank (9) by turning the quick air shutoff
valve (red handle) to the Ext. position to dump air pressure.
Note: Allow all of the pressure to drain from the tank before proceeding.
2. When the pressure gauge displays zero, evenly unthread the three handles on top
of the tank until they are loose from the tank top.
Note: The handles will remain connected to the tank lid.
3. Slowly remove the tank lid assembly and wipe fluid from the bottom of the dip
tube.
Note: Fluid may continue to drip from the tube.
4. Remove the empty bottle of fluid from the tank and discard.
5. Remove the cap of the next bottle and place it in the center of the tank.
6. Replace the lid assembly onto the tank, being sure the dip tube inserts into the
fluid bottle.
7. Tighten the three handles down evenly for an air tight seal.
Shut Down Procedure
1. At the end of the day or shift, remove air pressure on the fluid tank (9) by turning
the quick air shutoff valve (red handle) to dump air pressure.