Micron Installation V9 Power Up Sequence.pdf - 第3页

POWER UP SEQUENCE MACHINE POWER UP SEQU ENCE Chapter Issue 8, Jan 16 Installation Manual 5.3 3. Click on the Change date and time ... button. 4. Select the correct date on the calendar display . 5. Set the correct time o…

100%1 / 10
POWER UP SEQUENCE
MACHINE POWER UP SEQUENCE
5.2 Installation Manual Chapter Issue 8, Jan 16
MACHINE POWER UP SEQUENCE
Apply Systems
Power
1. Connect the pneumatic supply to the connection on the rear, bottom left of
the machine, External Services the Services Required chapter refers.
2. Connect the mains supply to the machine.
3. Turn the Mains Isolation Switch ON.
4. Select Diagnostics.
5. Ensure that System is highlighted and select Select Module.
6. Select the Previous button once to highlight Terminate Control Program.
7. Select Run Diagnost.
Time and Date
(Windows 7)
In order for the machine PC to log events correctly, the system time, date and
correct time zone must be set.
1. Using the mouse, click on the time, displayed at the right hand side of the
Windows taskbar. The following window is displayed:
2. Click on Change date and time settings...
POWER UP SEQUENCE
MACHINE POWER UP SEQUENCE
Chapter Issue 8, Jan 16 Installation Manual 5.3
3. Click on the Change date and time... button.
4. Select the correct date on the calendar display.
5. Set the correct time on the digital display beneath the clock.
6. Select OK.
POWER UP SEQUENCE
MACHINE POWER UP SEQUENCE
5.4 Installation Manual Chapter Issue 8, Jan 16
7. Select Change time zone....
8. Using the drop down box, select the appropriate time zone.
9. Select OK.
10. Select OK.
11. Select Start on the taskbar.
12. Select DEK Printer Software.
13. Press the System button.