1 Installation 1-6 Filter Regulator Air Coupler 65SN or 85SN Air Coupler

100%1 / 58
1 Installation
1-5
ACTION:
Locate the machine to the specified place.
Adjust the conveyor height to 900±20mm (or 950±20mm for SMEMA standard) by rotating the
adjust feet.
900±20mm
or
950±20mm(SMEMA)
Place a level on the machine base and adjust the height so that the machine is level lengthwise and
crosswise.
When the conveyor has become level, check if the height is 900±20 mm (or 950±20mm). Then fix
the adjust feet with nuts.
The head assy. is fixed to the XY shafts with nylon ties. Take them off with nippers.
Connect the power cable and ground line independently of other machines which may be a noise
source, such as a compressor, welding machine.
Connect the air supply coupler 65SN or 85SN (Nitto) or an alternate to the air coupler on the filter
regulator in the machine. Then, make sure the filter regulator indicates 0.49 MPa (5 kgf/cm
2
).
1 Installation
1-6
Filter Regulator
Air Coupler 65SN or 85SN
Air Coupler
1 Installation
1-7
Pre-Process and Post-Process of Machine
Connecting Pre-Process and Post-Process
When using other manufacturer’s machines as the pre-process or post-process, connect them as shown in
the below diagram. No-voltage output (relay) is recommended for post-process.
Standard spec. : Upper half of the diagram.
SMEMA Interface spec. : Whole diagram.
INPUT
CIRCUIT
INPUT
CIRCUIT
2
1
CN2 CN1
Post-process
Connector (Cable side)
AMP
206044-1(plug)
66099-2 or equivalent (pin)
206070-1(cable clamp)
Connector (Machine side)
AMP
206043-1(receptacle)
Machine Pre-process
BOARD
AVAILABLE
BOARD
AVAILABLE
MACHINE
NOT READY
2.2KΩ
10KΩ
10KΩ
10KΩ
10KΩ
COM
Input
terminal
*INPUT CIRCUIT
+5V
30VDC 1A or less
100VAC 0.5A or less
RELAY
RELAY
MACHINE
NOT READY
3
4
2
1
3
4