1OM-1603 3-5 1. Automatic Operation : Chap.3 1003-003 1.2 Preparation before Automatic Operation 1.2.1 Power ON Procedure (1) Remove the padlock from the lock lever of the power breaker located on the front side of the m…

1OM-1603
3-4
1. Automatic Operation : Chap.3
1003-003
1.1.4 SafetyConrmationofMachineSurroundings
Check the surroundings of the machine and conrm safety before starting the
automatic operation.
CAUTION
Before operating the machine, conrm that there are no
people around the machine (especially, the other side of
the machine operation) and no objects such as tools and
parts are left around the machine.

1OM-1603
3-5
1. Automatic Operation : Chap.3
1003-003
1.2 Preparation before Automatic Operation
1.2.1 Power ON
Procedure
(1) Remove the padlock from the lock lever of the power breaker located on the
front side of the machine.
Power Breaker
Lock Lever
Padlock
F1C4
(2) Set the power breaker to "ON".
(Power is supplied to the machine.)
Power Supply
F1C5
NOTICE
When the power must be supplied again, wait for
approximately 10 seconds after the power breaker is
set to "OFF", then set the breaker to "ON".
If the power breaker is set to "ON" soon after being set
to "OFF", the data collected before the power is turned
off will not be reset, causing the machine to malfunction
occasionally.

1OM-1603
3-6
1. Automatic Operation : Chap.3
1012-004
1.2.2 Preparation for Components
Procedure
(1) Detach the bank feeder change cart.
Reference
Refer to "2.2.5 Feeder Bases and Bank Feeder Change Cart" in Chapter 3
for details.
(2) Install the feeders in the feeder base.
Note
Before installing the feeders, check which types of feeders should be
installed in which feeder slot Nos. (Fdr No.).
Reference
Refer to the instruction manual of the tape feeder for the detailed
information on how to attach or detach the feeder.
WARNING
Those who wear implanted pacemakers are not
allowed to handle the tape feeders.
The pacemaker may be affected by the magnetism
and a serious accident will result.
NOTICE
Install the feeders correctly such that they are seated
properly.
Otherwise, they may collide with the head sections or a
pickup error will occur.
Be sure to install a feeder to the correct feeder slot
(Fdr No.).
Otherwise, some components may be trapped between the
heads.
(3)
Attach the bank feeder change cart to the machine.
Reference
Refer to "2.2.5 Feeder Bases and Bank Feeder Change Cart" in Chapter 3
for details.
1.2.3 Preparation for PCBs
In the case of normal automatic operation, conrm that PCBs are prepared in the
input machine.
•
When this ma
chine is operated singly (for an actual mounting test, etc.,),
follow the steps below.
Procedure
(1) Open the transparent covers located over the beams.
(2) Set the PCB on the position where the transferred PCB detection sensor is
turned ON (red light) when a PCB is set on the PCB input section.