7. Manually operate the feed lever and make sure the chips are correctly aligned on the belt. 8. Continue operating the feed lever until the first chip is at the pickup position. Unloading Pr ocedure 1. To return the par…

Loading and Removing Parts
Loading Procedure
• Use chips supplied in an EIAJ case.
• Perform the following procedure to load
parts from the EIAJ case into the bulk
feeder’s hopper.
(The numbers in the illustrations refer to
steps in the procedure.)
1. Press the EIAJ case down on the stopper
(white button).
2. Slide the EIAJ case horizontally until the
stopper clicks up, locking the case into
position.
3. Raise the lever on the side of the EIAJ
case and allow all the chips to fall into the
hopper.
4. Gently shake the feeder from side to side
to distribute the chips evenly inside the
hopper.
5. Gently press
the stopper
down and let
the feeder
eject the EIAJ
case.
6. Insert the empty EIAJ case in the empty case holder at the rear of the bulk feeder,
to allow identification of the chips being used.
Note: Make sure that the EIAJ case is completely empty prior to insertion into the holder.
Loading and Removing Parts
Version 3.0 2 CP-6 Bulk Feeder Instruction
(2)
(1)
BF001
(4) Surface should be
roughly level.
(4) Shake from
side to side.
(3)
BF002
(5)
(5)
BF003
Insert in empty case holder
(6)

7. Manually operate the feed lever and make sure the chips are correctly aligned on
the belt.
8. Continue operating the feed lever until the first chip is at the pickup position.
Unloading Procedure
1. To return the parts in the bulk feeder’s hopper to the EIAJ case, reattach the empty
case and hold the feeder upside down until the hopper is empty of parts.
2. Remove the bolt that secures the pickup area cover on the front of the feeder, then
lift the cover open. If there is a chip attached to the magnetic lever, remove it.
3. Keeping the cover open, manually operate the feed lever and remove any parts
that are indexed forward on the belt.
4. When you are satisfied there are no more chips under the pickup area cover, close
the cover and secure it with the bolt. Be careful not to force the cover shut, or it
may be damaged.
Note: When replacing chips with parts made by a different manufacturer, make sure that all the
previous parts have been removed from the hopper, belt, and pickup area before supplying
new parts.
Lift open.
Cover
Cover bolt
Lever
BF004
Loading and Removing Parts
Version 3.0 3 CP-6 Bulk Feeder Instruction

Cleaning and Lubrication
Cleaning
After long periods of use, the operation of the feeder may be adversely affected by dust
and by minute metal particles resulting from friction between the parts in the hopper.
The parts listed below should therefore be cleaned every month or after the supply of
500,000 parts, whichever comes first. Perform the following procedure to clean the bulk
feeder.
• Begin by removing the seven bolts securing the stainless steel plate on the side of
the bulk feeder, then remove the plate.
1. Clean the bushing.
• Remove the two bolts (A), then pull the hopper upward to remove it. (Be careful
not to lose the spring when removing the hopper.)
• Pull the bushing out from the bottom of the hopper.
• Apply fine compound (#240 or higher) to a cotton swab and carefully remove any
black metal particles from the inside of the bushing.
Outer pipe
Pipe retainer
Bolt A
Hopper
Bolt A
Inner pipe
Bushing
Bolt B
Bolt C
BF006
Stainless steel plate
BF005
Cleaning and Lubrication