1 Installation 1-3 How to Hoist the Machine Use the wires and the arm as follows. NOTE: Be sure to use the arm to preven t the wire from touching the machine. Front View Arm Wire Side View Arm Wire

1 Installation
1-2
Installation of Machine
Environmental Requirements
Install the machine at the place where the below conditions are met.
Do not do tasks, such as moving the machine or connecting the machine with the main switch ON to
prevent electric shock.
■ Ambient Temperature: Accuracy assurance 23 +/-2 degrees centigrade
Operation assurance 5 to 40 degrees centigrade
(The average over a period of 24 hours does not exceed 35 degrees C.)
■ Relative Humidity: 45 to 60 percent, non-condensing
■ Altitude: 1,000 or below above sea level
■ Atmosphere: Dust and corrosive gas free
■ Floor: Floor must be flat and sturdy enough for freedom from vibration during
operation.
■ Power Requirements: 200 VAC +/- 10%, three phase, 50/60 Hz
* 208/220/230/240/380/400/415/440V VAC with optional power
transformer
Power consumption: 0.77KW
Installed capacity: 2.01kVA
Leakage current: 20mA or less
* Power and ground the machine independently of other machines which may be a
noise source, such as a compressor, welding machine, or reflow soldering machine
with magnetic contacts.
Warning

1 Installation
1-3
How to Hoist the Machine
Use the wires and the arm as follows.
NOTE: Be sure to use the arm to prevent the wire from touching the machine.
Front View
Arm
Wire
Side View
Arm
Wire

1 Installation
1-4
■ Recommended Bolt Size
● Type 1 (M20 x P2.5)
● Type 2 (M20 x P2.5)
MxP D d d1 L2 L3 S T L R H B C
Type1 Type2
Type1 Type2
20x 2.5
25 48 62 20 28 37 32 16 90 98 2 12 17 19.8