M6ex_ServiceManual_e.pdf - 第14页
1 Installation 1-6 Installing the Machine Do not touch terminals of electric com ponents when the power is on to prevent electric shock and m achine damage. Make sure to ground the machi ne to prevent electric shock. Not…

1 Installation
1-5
Production Line
To align your assembly line, first install the heaviest unit. Then install peripheral units using the first unit as
a reference.
Reference
Loader Mounter Reflow Oven Conveyor Unloader
To transfer the PCB (printed circuit board) smoothly, clearance between units are quite important. Be sure
that the clearance between units is 5 mm or less as below figure shows. Adjust the height of the downstream
unit a little lower (0-0.5 mm) so that the PCB is transferred smoothly.
0 - 0.5mm
5mm or less
Downstream Upstream
側

1 Installation
1-6
Installing the Machine
Do not touch terminals of electric components when the power is on to prevent electric shock and machine
damage.
Make sure to ground the machine to prevent electric shock.
Note on Installation
It is normal that the adjust foot can be slightly inclined (within 2-degree range).
Do not tighten the bolt forcedly trying to fix the foot.
When you move and/or install the mounter, be careful not to apply excessive
force on the adjust foot. This may cause the screw of the adjust foot to break.
When placing the mounter on the floor, be sure that the mounter is kept
horizontal.
Warning
Warning
2°
If excessive force is
applied, the screw may
break at this point.
Mounting Screw
Nut
Adjust foot

1 Installation
1-7
ACTION:
① Locate the machine to the specified place.
② Remove the followings: the bolt that locks the head in the X-axis beam, the metal fitting that locks the
Scan Camera and the nylon ties that prevent X-axis beam movement to the Y direction. Check to see
that the head and the Scan Camera can move to the X direction and the X-axis beam can move to the
Y direction manually.
③ When the machine is installed stand alone, turn the adjust feet so that the PCB transfer height is the
same as the conveyor height (900±20mm (see Note)) of the reference equipment.
When the machine is connected to the Pre-process on production line, adjust the PCB transfer height
to the conveyor rail height of the Pre-process.
)
Production Line
In the case of SMEMA interface spec, the height must be 950±20mm.
900+/-20mm
or
950+/-20mm(SMEMA)
NOTE: The height must be 890 to 920mm in the case of CFB wagon spec.
NOTE: The adjust feet must be turned using a M30 single-head wrench (nominal: 46mm).
④ Place a leveler on the base of the machine. Set the position to the conveyor of the Pre-process finely
until the machine is leveled.
) Supplementary Explanation for Installation
Leveler