M6ex_ServiceManual_e.pdf - 第12页
1 Installation 1-4 ■ Recommended Bolt Size ● Type 1 (M20 x P2.5) ● Type 2 (M20 x P2.5) MxP D d d1 L2 L3 S T L R H B C Type1 Type2 Type1 Type2 20 x 2.5 25 48 62 20 28 37 32 16 90 98 2 12 17 19.8 [Unit = mm]

1 Installation
1-3
How to Hoist the Machine
Use the wires and the arm as follows.
NOTE: Be sure to use the arm to prevent the wire from touching the machine.
Front View
Arm
Wire
Side View
Arm
Wire

1 Installation
1-4
■ Recommended Bolt Size
● Type 1 (M20 x P2.5)
● Type 2 (M20 x P2.5)
MxP D d d1 L2 L3 S T L R H B C
Type1 Type2
Type1 Type2
20x 2.5
25 48 62 20 28 37 32 16 90 98 2 12 17 19.8
[Unit = mm]

1 Installation
1-5
Production Line
To align your assembly line, first install the heaviest unit. Then install peripheral units using the first unit as
a reference.
Reference
Loader Mounter Reflow Oven Conveyor Unloader
To transfer the PCB (printed circuit board) smoothly, clearance between units are quite important. Be sure
that the clearance between units is 5 mm or less as below figure shows. Adjust the height of the downstream
unit a little lower (0-0.5 mm) so that the PCB is transferred smoothly.
0 - 0.5mm
5mm or less
Downstream Upstream
側