Keysight i3070 Series 6 In -Circuit Test System Site Preparation Power Requirements Customer Responsibilities 6-2 About the PDU 6-2 Po we r R e qu ire me n ts 6-3 Is PDU Re-wiring Necessary? 6-8 PDU Wiring Diagrams 6-9

5-4 Site Preparation
5 Environmental Requirements
Cooling Requirements
Design the site cooling capability using the heat dissipation estimates in Table 5-2.
Humidity Requirements
The system is designed to operate in the range from 5% to 80% relative humidity
(non-condensing).
If the system is subjected to condensation, as if moved from a cold loading dock
into a warm environment, allow at least 24 hours for the system to recover before
powering up.
Table 5-2 System heat dissipation
Number of Modules Dissipation
1 module 10500 BTU (3.1 kW)
2 modules 19700 BTU (5.8 kW)
3 modules 28500 BTU (8.4 kW)
4 modules 3700 BTU (10.9 kW)

6-2 Site Preparation
6 Power Requirements
Customer Responsibilities
It is the customer’s responsibility to (a) prepare the site with adequate AC power for
the system, and (b) connect the system to the AC power source. These are not
Keysight’s responsibilities.
Read Power Requirements on page 6-3. In most cases this section will describe all
you need to do to prepare your site.
About the PDU
The PDU (Power Distribution Unit) is the device in the system to which you will
connect AC power.
The PDU is wired differently for different power configurations. The voltage of the
PDU is marked on the front panel of the PDU. If you install a system in a location in
which the actual power does not match the power configuration of the PDU, you
may need to rewire the outlet connections in the PDU (see Is PDU Re-wiring
Necessary? on page 6-8).
After connecting power to the system, do not power up the
system. A Keysight service representative will verify the
power and complete the system installation and verification.