Fini sh p r oduction and chang e w o rk Chap ter 5 Advanced Chip Shooter DE CAN S2 O pe rat ion H an db ook 5-5 This chapter describes the method to finish production and change t he work to new work as well as the metho…

Finish production and change work
Chapter 5
Advanced Chip Shooter
DECAN S2 Operation Handbook
5-4
This chapter describes the method to finish production and change the
work to new work as well as the method to turn off the power supply
to the machine after finishing production and keeping the area around
the machine clean and tidy.
SMT In-Line Process > Finishing the Production and shutting down the machine
SMT In-Line Process
Finish production and change work
Magazine Loader
Screen Printer
Component Placer
Component Placer
Work Table
Reower
Magazine Unloader
Work Sequence In-Line System Measures
1 Magazine Loader Adjust the conveyor width according to the width of the PCB to be newly worked on
2 Screen Printer
Machine Stop → Metal Mask Removal/ Washing → Backup Pin Removal → New
Work File Loading → Backup-Pin Rearrangement → Conveyor Width Adjustment →
Metal Mask Installation → Solder Check/ Make-up
3 Component Placer For more details, refer to the section entitled Changing Jobs on the next page.
4 Work Table Adjust the conveyor width according to the width of the PCB to be newly worked on
5 Reflower Conveyor Width Adjustment → Test Production → Setups for Temperature and others
6 Magazine Unloder Adjust the conveyor width according to the width of the PCB to be newly worked on
SMT In-Line Process

Finish production and change work
Chapter 5
Advanced Chip Shooter
DECAN S2 Operation Handbook
5-5
This chapter describes the method to finish production and change the
work to new work as well as the method to turn off the power supply
to the machine after finishing production and keeping the area around
the machine clean and tidy.
Changing Jobs > Changing the machine status into the 'IDLE' mode
Changing Jobs
1. Changing the machine status into the 'IDLE' mode
Step 1.
Press the 'STOP' button
Step 2.
Press the 'RESET' button
Step 3.
Check if the machine is in the 'IDLE' mode
Changing Jobs

Finish production and change work
Chapter 5
Advanced Chip Shooter
DECAN S2 Operation Handbook
5-6
This chapter describes the method to finish production and change the
work to new work as well as the method to turn off the power supply
to the machine after finishing production and keeping the area around
the machine clean and tidy.
Changing Jobs > Removing the feeder
Changing Jobs
Finish production and change work
2. Removing the feeder
Step 1.
Pull the grip back
Step 2.
Remove the cover tape
Step 3.
Remove the feeder