_482615_RE1304003 8mm ZS feeder maint.pdf - 第21页

Trained Customers Service Information 21 / 27 SI 1304003E- 00 0 = 8mm ZS feeder maintenance procedures 1 2.12 Replace the P/O1 roller , P4 and P5 idle gears Note Each of those gear s can be replaced separatel y; the y do…

100%1 / 27
Trained Customers
Service Information
20/27
SI1304003E-000 = 8mm ZS feeder maintenance procedures 1
2.11.2 Install the EL box
Step 1 Install the connector interfaced with the machine by screwing (tightening torque
30Ncm) using Loctite 241. Also install the feeder board assy by screwing (tightening
torque 20Ncm).
Use a Phillips screwdriver (No.1).
Step 2 Fit the nut plate on the limit switch so that the limit switch’s protruded part is inserted
in the nut plate’s hole. Then fasten the limit switch with a screw using a 1.5 hex
wrench.
Apply Loctite 241 on the screw and tighten it to 30Ncm.
Step 3 Fit the EL box onto the feeder frame by inserting the EL box’s positioning pin into the
feeder frame’s mating hole.
Step 4 Fasten the EL box with three screws using a Phillips screwdriver (No.2).
Tighten the screws to 75Ncm.
Step 5 Connect the limit switch to the feeder board assy at its connector.
Route the limit switch harness over the mount screw of the EL box.
Step 6 Place the cable cover on the EL box. Then install the earth cable of the peel motor on
the feeder body with a screw using a Phillips screwdriver (No.1).
Tightening torque of the mount screw is 40Ncm.
Note
The cable cover must be placed on the correct position to avoid its interference with mount
holes of the feeder side cover and others.
Step 7 Connect the harnesses from the feed motor, ABS board, peel motor, operation switch
and splice sensor (optional) to the feeder board assy at respective connectors.
Step 8 Install the feeder side cover referring to “2.4 Replace the feeder side cover”, step 2.
Step 9 Install the EL box cover referring to “2.3 Replace the EL box cover, step 2.
Positioning holes
Positioning pins
Trained Customers
Service Information
21/27
SI1304003E-000 = 8mm ZS feeder maintenance procedures 1
2.12 Replace the P/O1 roller, P4 and P5 idle gears
Note
Each of those gears can be replaced separately; they do not need to be replaced as a set.
2.12.1 Remove the P/O1 roller, P4 and P5 idle gears
Step 1 Remove the top tape box cover referring to “2.2 Replace the top tape box cover”,
step 1.
Step 2 Remove the two screws fastening the “Idle gear 2” cover using a Phillips screwdriver
(No.1) then remove the “Idle gear 2” cover from the feeder body.
Note
It is recommended to insert a precision screwdriver under the cover to remove it, as it is
difficult to remove because of the two positioning pins.
Remove the two screws fastening the P/O tooth 1 block with a hex wrench (Size 2).
Step 3 Insert a scale between the P/O lever assy gear and the feeder body. Then remove the
P/O tooth 1 block and the P/O 1 roller. (Pull them together little by little to remove from
the feeder body.)
Step 4 Remove the three screws fastening the “Idle gear 1” cover with a Phillips screwdriver
(No.1). Then remove the cover from the body.
Step 5 Remove the P4 and the P5 idle gears.
Idle gear 2 cover
P/O tooth 1 block
P/O1 roller
P/O Tooth 1 block
Idle gear cover
P4
P5
Trained Customers
Service Information
22/27
SI1304003E-000 = 8mm ZS feeder maintenance procedures 1
2.12.2 Install the P/O1 roller, P4 and P5 idle gears
Apply a tiny amount of NSK NSL grease at where relevant positioning pins and gears come in
contact.
Note
Do not apply grease to the gear section. If the gear is contaminated with grease, wipe the
gear clean.
Step 1 Set the Idle P4 gear to the shaft close to the EL box so that the side with more teeth
faces down.
Step 2 Set the Idle P5 gear to the upper shaft so that the side with fewer teeth faces down, and
then rotate the gears slightly in order to mesh them properly.
Step 3 Fit the Idle gear 1 cover into the holes of the positioning pins, and fasten the cover
with three screws using a Phillips screwdriver (No.1). Tightening torque is 40Ncm.
Step 4 Insert a scale between the P/O lever assy gear and the feeder body to install the P/O
tooth 1 block and P/O 1 roller.
Note
Insert the claw of the P/O tooth 1 block into the groove of the P/O 1 roller, then set them
together little by little to the feeder body.
Fasten the P/O Tooth 1 block to the feeder body with two screws using a hex wrench (Size 2).
Tightening torque is 20Ncm.
Step 5 Remove the scale and rotate the P/O lever gear to check that the gear rotates
smoothly.
Step 6 Fit the “Idle gear 2” cover into the holes of the positioning pins, and fasten the cover
with two screws using a Phillips screwdriver (No.1). Tightening torque is 40Ncm.
Step 7 Install the top tape box cover to the feeder body referring to “2.2 Replace the top
tape box cover”, step 2.
P4
P5
Positioning hole
Scale