Introduction
Document Purpose / Target Group
SIPLACE SiCluster Multiline SIPLACE SiCluster Multiline 103
1
1 Introduction
Introduction
SiCluster Multiline is an optimization tool for planning setups. This manual describes the concept and
use of SiCluster Multiline.
1.1
1.1 Document Purpose / Target Group
Document Purpose / Target Group
We recommend that you read through this manual carefully, even if you are already familiar with the
main SiCluster Multiline functions. This manual includes all key information about SiCluster Multiline and
its connections to other systems. Practical examples guide you "step by step" through the basic functions
of SiCluster Multiline. At the end of this document, you will be able to master the main tasks with SiClus-
ter Multiline. You can then build upon this knowledge in training sessions and learn about further func-
tions.
The contents of this manual address the following user groups:
The production planner
The production planner has completed a special training course and is authorized to perform tasks
such as setup and production planning, defining optimization parameters etc.
1.2
1.2 Symbols / Notes
Symbols / Notes
Different symbols and notes have been used to make it easier to read and understand this document.
CAUTION
Trained and qualified personnel
Only people with the appropriate training for the specific software part may carry out tasks on
the machine. All tasks must be carried out by trained and qualified personnel. All warning, cau-
tion and danger notes MUST be observed!
CAUTION
Contents of this software guide
We would like to draw your attention to the fact that the contents of this software guide are not
part of a previous or existing agreement, commitment or legal contract, neither is this intended
to modify one of the above. All obligations of ASM Assembly Systems GmbH & Co. KG may be
taken from the appropriate sales contract, which also contains a complete and valid warranty
agreement. These contractual statements are neither extended nor restricted by this software
guide.
Words in bold/italic print These refer to dialogs, dialog fields, menu items, and commands.
Step ... Includes all actions to do with a particular dialog. A dialog may be
composed of several actions ().
Requires an action (e.g. mouse click, open file)
Indicates a warning. The information is essential for successful
working.
Explanatory information.
Introduction
SIPLACE on the World Wide Web (WWW)
104 SIPLACE SiCluster Multiline SIPLACE SiCluster Multiline
1.3
1.3 SIPLACE on the World Wide Web (WWW)
SIPLACE on the World Wide Web (WWW)
Log into our SIPLACE® homepage at http://www.siplace.com.
You can choose between the German and English versions.
The different sections contain information about our products, services and contact persons.
In addition, registered customers can access the
SIPLACE User Group
. Here you can call up special
information about our placement systems e.g.
Technical documentation,
Technical information,
Spare parts lists etc.
Registration for the user group is very simple:
Click on the Register link.
Fill in the registration form and send it off to us.
Soon afterwards, you will receive your access authorization with USER ID and password.
Introduction to SiCluster Multiline
What is SiCluster Multiline?
SIPLACE SiCluster Multiline SIPLACE SiCluster Multiline 105
2
2 Introduction to SiCluster Multiline
Introduction to SiCluster Multiline
2.1
2.1 What is SiCluster Multiline?
What is SiCluster Multiline?
SiCluster Multiline is a key component for program-controlled production planning.
SiCluster Multiline is used to determine the most efficient distribution of specified recipes/jobs across an
available quantity of lines. Based on an optimized product/recipe line allocation, you can then cluster
within the lines with the help of SiCluster Professional and optimize the result setups (cluster).
SiCluster Multiline therefore enables you to distribute numerous recipes/jobs across multiple lines, there-
by making it easier for the downstream optimization steps with SiCluster Professional and the result job
optimization to find good solutions.
SiCluster Multiline is designed to achieve the following goals:
Even utilization of lines
Lowest possible overall production time across all lines
Lowest possible number of setups required to produce the recipes/jobs
2.2
2.2 Who is SiCluster Multiline Designed For?
Who is SiCluster Multiline Designed For?
SiCluster Multiline is particularly suitable for the three following areas of application:
1. Medium to long term capacity planning for fixed family setups
2. Evaluation of "what if" planning scenarios
3. Short term distribution and clustering of upcoming production jobs
Medium to long term capacity planning for fixed family setups
In this case, the customer has medium to long term advance planning for the expected production jobs.
This could, for example, include advance planning for the next three to six months.
SiCluster Multiline is used to optimize the allocation of production jobs to the production lines. This allo-
cation is then fixed for a longer period. The aim is to produce as many production jobs as possible in
fixed setups. The software takes into account the prescribed restrictions and creates an even distribution
of the production volume across the lines.
You can also check whether the line capacity currently available is sufficient to cover the expected ad-
vance planning volumes for a certain period.
Evaluation of "what if" planning scenarios
SiCluster Multiline is suitable for so-called "what if" planning scenarios.
These planning scenarios are needed in case changes must be made to the production capacity or line
configuration.
Examples of "what if" planning scenarios:
Can the expected production volume be produced with the current shift plans or are additional shifts
required?
Could we shut down line X for the next two months?
What would be the advantage of replacing an old line with a new SIPLACE line?
Is is advisable to remove machines from line X, in order to extend line Y, Z?
Short term distribution and clustering of upcoming production jobs
The two above mentioned application cases focus on using medium to long term advance planning.
However, SiCluster Multiline is also suitable for short term planning if you already know the upcoming
production jobs for a certain planning horizon e.g. for several days or a week.
The aim is to produce all production jobs with as few setups as possible in the shortest possible time.
In these cases, flexible family setups are used, which are then only used for producing the current pro-
duction jobs. The allocation to these production lines is flexible. The next time, SiCluster Multiline could
allocate the production job for the same product to a different line.