5-4 Site Preparation
5 Environmental Requirements
Humidity Requirements
The system is designed to operate in the range from 5% to 80% relative humidity (non-condensing).
If the system is subjected to condensation, as if moved from a cold loading dock into a warm
environment, allow at least 24 hours for the system to recover before powering up.

6-2 Site Preparation
6 Power Requirements
Customer Responsibilities
It is the customer’s responsibility to (a) prepare the site with adequate AC power for the system, and
(b) connect the system to the AC power source. These are not Keysight’s responsibilities.
6 Read About the PDU on page 6-3. You must know where the system’s PDU is located to prepare
your site.
7 Read Power Requirements on page 6-4. In most cases this section will describe all you need to
do to prepare your site.
8 If you are connecting the system to a different power configuration than it is wired for, read Is
PDU Re-wiring Necessary? on page 6-9.
After connecting power to the system, do not power up the system. A Keysight service
representative will verify the power and complete the system installation and
verification.