It is possible to set the sequence from which production is to start. This oper- ation must be carried out with the panel on the XY -table. Procedure 1. Select [Production] from the [Main] screen. 2. Then select [Start S…

100%1 / 91
It is possible to operate a servo control axis via a manual operation. This oper-
ation is called "inching".
Procedure
1. Select [JOG…] from the command bar at the bottom of any
screen.
2. Select the desired axis from the [Select Axis Set] section.
3. Move the servo axis as desired using the inching keys.
Note: Rapid inching can be performed by holding down the [F] key while
pressing the appropriate arrow key.
Changing the Rapid Inching Speed
Procedure
1. Select [JOG…] from the command bar at the bottom of any
screen.
2. Select the desired axis from the [Setting Speed] section.
3. Use the numeric keypad to input the speed (expressed as a per-
cent of the full speed of the servo axis).
Note: The inching speed cannot be changed by more than 5%.
4. Then press [OK].
8.1 Manual Operation of Servo Control Axes
Chapter 8: Production Support Functions
Preliminary
8-2 CP-842E/842ME Operator’s Guide
It is possible to set the sequence from which production is to start. This oper-
ation must be carried out with the panel on the XY-table.
Procedure
1. Select [Production] from the [Main] screen.
2. Then select [Start Sequence].
3. Select [Production Start Number].
4. Use the numeric keypad to input the number of the sequence
from which production is to start.
5. Press the START button.
Note: If fiducial mark acquisition has not been completed for the panel on the
XY-table, production will start from the specified sequence but after the
fiducial marks are read.
8.2 Setting the Production Start Sequence
Chapter 8: Production Support Functions
Preliminary
8-3CP-842E/842ME Operator’s Guide
A new panel can be loaded onto the XY-table by means of a command opera-
tion. This can also be used when a panel is already on the XY-table and the
new panel is to be loaded after the existing panel is unloaded. The panels can
be changed using the following operation.
Procedure
1. Select [Panel Loader] from the [Setup] section at the [Main]
screen.
2. Select [Load Panel].
3.
Press the START button.
All panels from the XY-table to the out-conveyor can be unloaded. Remove
the panels in order as they are unloaded to the out-conveyor.
Procedure
1. Select [Panel Loader] from the [Setup] section at the [Main]
screen.
2. Select [Unload] from the [Load/Unload] section.
3. Press the START button.
8.4 Unloading Panels From the XY-table
8.3 Loading a New Panel
Chapter 8: Production Support Functions
Preliminary
8-4 CP-842E/842ME Operator’s Guide