12 2.2 Integration into the prod uct life cycle The VDA 6.3 audit standard can be u sed throughou t the entire produ ct life cy- cle, from the selection of potential suppliers (P1 potential a nalysis) and the product and…

100%1 / 107
11
product characteristics, this should be documented and taken into account in
the evaluation.
Table 2-1: Differentiation between audit standards
Copyright by VDA QMC
12
2.2 Integration into the product life cycle
The VDA 6.3 audit standard can be used throughout the entire product life cy-
cle, from the selection of potential suppliers (P1 potential analysis) and the
product and production process development (P2-P4) up to support during
series production and follow-up support after production (P5-P7). Thanks to
the modular structure of the volume, individual process elements can also be
audited depending on the scope to be considered.
Figure 2-1 shows the possible use of the individual process elements accord-
ing to VDA 6.3 and how they relate to VDA MLA and Automotive SPICE
®
standards.
Figure 2-1: Possible use of the individual process elements
P1: Potential analysis
P2: Project management
P3: Product and production process development planning
P4: Implementation of product and production process development
P5: Supplier management
P6: Production process analysis
P7: Customer care, customer satisfaction, service
For explanations regarding the potential analysis, see chapter 5.
The use of process elements P2 to P4 focuses on the phase of the product
and production process development. Ideally, both process element P2 and
process element P3 are used after contract award to analyze the planning ac-
tivities.
Copyright by VDA QMC
13
Process element P4 can be used at a later time to analyze and evaluate the
implementation of the planning activities in accordance with process element
P3.
The breakdown of the process elements provides the opportunity to assess
the planning activities as well as the implementation/realization in accordance
with the requirements. From the contracting stage including SOP, the use of
process elements P2 to P4 serves to identify maturity level and process risks
early on.
Process elements P5 to P7 are ideally used at the time of the milestone SOP.
This corresponds to maturity level ML 6 from VDA MLA. As part of series pro-
duction, process elements P5 to P7 can be used to regularly monitor the se-
ries production processes and the processes after discontinuation of the se-
ries, or to support an event-based reactive process analysis.
In principle, each organization has the right to adapt the use of the process
elements so as to meet their needs during product and production process