68 P4.9* Is there a controlled method for the project handover from development to series production? Minimum requirements relevant for assess- ment Examples for implementation There is a process for transferring work re…

67
P4.8 Have the processes for ensuring customer care/customer satisfac-
tion/customer service as well as the field failure analysis been estab-
lished?
Minimum requirements relevant for assess-
ment
Examples for implementation
The customer requirements regarding the supply
of parts throughout the product life cycle are es-
tablished in the processes.
The planned processes for the continuous series
supply including safety margins for emergencies
are available.
The analysis process for 0-km and field com-
plaints is established for the scope of delivery.
The customer requirements regarding field failure
analysis are taken into account.
The requirements for the analysis capability at
the site have been agreed with the customer.
If external sites are used for analysis, the inter-
faces are defined and evidence of the availability
of the required equipment and capacity is availa-
ble.
New technologies and products are also taken
into account in customer support.
The employees designated for these processes
are qualified. The infrastructure is available.
Processes for product monitoring in the field have
been specified.
There must be processes for error analysis and
diagnosis (embedded software in control unit).
If agreed, processes for over-the-air (OTA) soft-
ware updates have been specified.
Product/process development
• Inspection equipment for
standard and stress tests
• Triggering criteria are defined
• Inspection plans for failure
analysis
• NTF process
Process development
• Qualification matrix and evi-
dence of training
• Inspection equipment
• Service agreements with exter-
nal analysis sites
• Spare parts supply concepts
• Contingency plans
Copyright by VDA QMC

68
P4.9* Is there a controlled method for the project handover from development
to series production?
Minimum requirements relevant for assess-
ment
Examples for implementation
There is a process for transferring work results
from the project to series production.
The activities specified in the project plan have
been implemented. Deadlines have been set for
aspects that are still to be clarified, and responsi-
ble persons have been appointed.
Successful internal release and customer release
is a prerequisite for a series delivery release.
Measures resulting from internal and external re-
leases are implemented on time.
Personnel are available in accordance with the
planning and are qualified.
The material resources for series production are
available in accordance with the planning.
Measures to secure the production start-up have
been specified and introduced.
For products with integrated (embedded) soft-
ware, the results from development (including in-
termediate results and their documentation) are
recorded.
The industrialization is ensured.
Product/process development
• Customer requirements
• PPA records
• Handover protocols/checklists
with handover criteria, ac-
ceptance reports
• Parts history
• Key production figures such as
OEE, ppm, reject rate, etc.
• Experiences from the ongoing
project
• Personnel resources (produc-
tion staff, process engineers,
maintenance, etc.)
• Material resources (machines
and plants, buildings, access
routes, inspection facilities,
load carriers, packaging, etc.)
• Change log, Release Note
• Industrialization of software: in-
cludes flashing software onto
the control unit in series pro-
duction and coding
Copyright by VDA QMC

69
7.5 Supplier management (P5)
Process element P5: Supplier management
P5.1 Are only approved suppliers used who are able to meet the quality re-
quirements?
Minimum requirements relevant for assess-
ment
Examples for implementation
In series production, it must be ensured that only
approved suppliers are used. The relevant ap-
proval criteria have been defined.
When selecting suppliers and in order to assess
their ability to meet quality requirements, a pro-
cess audit must be planned and carried out de-
pending on the risk classification of the compo-
nent.
Evaluations of the quality performance of existing
suppliers have been taken into consideration.
Risks in the supply chain (internal/external) have
been identified, evaluated and mitigated using
suitable measures.
In case of suppliers appointed by the customer
(directed suppliers), interface agreements are
taken into consideration.
• Defined criteria for the selection
of suppliers
• QM agreements
• In case of criteria that have not
been met: evidence of
measures being implemented in
order to mitigate risks
• Assessment of the suppliers’
ability to meet quality require-
ments, e.g. by means of KPI
(ppm, delivery performance),
escalation level
• Self-Assessment, audit results
of the suppliers
• ASPICE assessment results
• VDA 6.3-Process Audit
• VDA 6.3-Potential Analysis
Copyright by VDA QMC