67 P4.8 Have the processes for ensuring customer care/customer satisfac- tion/customer service as well as the field failure analysis been estab- lished? Minimum requirements relevant for assess- ment Examples for impleme…

66
P4.7 Is a performance test carried out under series conditions for the series
release?
Minimum requirements relevant for assessment
Examples for implementation
A performance test must be carried out under se-
ries conditions to confirm that the required quantity
can be produced for the customer with the re-
sources used, within the specified period of time
and in accordance with the specifications.
If the performance test fails to confirm this,
measures must be defined.
The installation of the software in the components
must be taken into account when determining the
cycle times/throughput times.
Note: Depending on the time of the audit, some
parts of the relevant production test could still be at
the planning stage!
The question is not relevant for product develop-
ment!
Process development
• Series production conditions:
e.g. tools, plants, cycle time,
personnel, production and in-
spection specifications,
measuring and inspection
equipment
• Customer requirements
• Performance test,
Run@Rate
• Determination of minimum
quantities (production peak
and agreed flexibility)
• Series production maturity of
equipment and facilities
(measurement report)
• Staff concept for series pro-
duction
• Packaging requirements
Software
• Flash times, including test,
ROM programming
Copyright by VDA QMC

67
P4.8 Have the processes for ensuring customer care/customer satisfac-
tion/customer service as well as the field failure analysis been estab-
lished?
Minimum requirements relevant for assess-
ment
Examples for implementation
The customer requirements regarding the supply
of parts throughout the product life cycle are es-
tablished in the processes.
The planned processes for the continuous series
supply including safety margins for emergencies
are available.
The analysis process for 0-km and field com-
plaints is established for the scope of delivery.
The customer requirements regarding field failure
analysis are taken into account.
The requirements for the analysis capability at
the site have been agreed with the customer.
If external sites are used for analysis, the inter-
faces are defined and evidence of the availability
of the required equipment and capacity is availa-
ble.
New technologies and products are also taken
into account in customer support.
The employees designated for these processes
are qualified. The infrastructure is available.
Processes for product monitoring in the field have
been specified.
There must be processes for error analysis and
diagnosis (embedded software in control unit).
If agreed, processes for over-the-air (OTA) soft-
ware updates have been specified.
Product/process development
• Inspection equipment for
standard and stress tests
• Triggering criteria are defined
• Inspection plans for failure
analysis
• NTF process
Process development
• Qualification matrix and evi-
dence of training
• Inspection equipment
• Service agreements with exter-
nal analysis sites
• Spare parts supply concepts
• Contingency plans
Copyright by VDA QMC

68
P4.9* Is there a controlled method for the project handover from development
to series production?
Minimum requirements relevant for assess-
ment
Examples for implementation
There is a process for transferring work results
from the project to series production.
The activities specified in the project plan have
been implemented. Deadlines have been set for
aspects that are still to be clarified, and responsi-
ble persons have been appointed.
Successful internal release and customer release
is a prerequisite for a series delivery release.
Measures resulting from internal and external re-
leases are implemented on time.
Personnel are available in accordance with the
planning and are qualified.
The material resources for series production are
available in accordance with the planning.
Measures to secure the production start-up have
been specified and introduced.
For products with integrated (embedded) soft-
ware, the results from development (including in-
termediate results and their documentation) are
recorded.
The industrialization is ensured.
Product/process development
• Customer requirements
• PPA records
• Handover protocols/checklists
with handover criteria, ac-
ceptance reports
• Parts history
• Key production figures such as
OEE, ppm, reject rate, etc.
• Experiences from the ongoing
project
• Personnel resources (produc-
tion staff, process engineers,
maintenance, etc.)
• Material resources (machines
and plants, buildings, access
routes, inspection facilities,
load carriers, packaging, etc.)
• Change log, Release Note
• Industrialization of software: in-
cludes flashing software onto
the control unit in series pro-
duction and coding
Copyright by VDA QMC