VDA_6.3_EN_Yellow_Volume_.pdf.pdf - 第54页

52 7.3 Product and process development planni ng (P3) Process element P3: Product and process development planning P3.1 Have the product/process-specific requirements been specified? Minimum requirements relevant for ass…

100%1 / 107
51
The deadlines for contract awards, supplier mile-
stones and release are included in the planning and
are coordinated so as to match the overall sched-
ule.
P2.6* Is change management within the project ensured by the project
organization?
Minimum requirements relevant for assessment
Examples for implementation
Change management within the project meets the
customer’s specific requirements.
Changes (initiated by the supplier, internally or by
the customer) must be evaluated. If necessary, the
project plan must be adapted. This evaluation must
include the risk assessment for product quality as
well as the deadlines.
Suppliers are actively involved in change manage-
ment.
It must be ensured that specified design freezes are
observed. Exceptions must be agreed upon be-
tween the customer and the supplier and must be
documented.
All changes must be documented.
The persons responsible for change management
are defined for the customer, internally and to sup-
pliers.
Change management
Process description
Schedules
Change forms
Change history for the prod-
uct and the process
Evaluation of changes
Approvals of changes
Software: Change request,
change management
Change due to fault elimina-
tion, changes to the architec-
ture and the requirements
52
7.3 Product and process
development planning (P3)
Process element P3: Product and process development planning
P3.1 Have the product/process-specific requirements been specified?
Minimum requirements relevant for assessment
Examples for implementation
The functional and non-functional requirements, in-
cluding the customer’s requirements as well as stat-
utory and regulatory requirements that apply to the
product (and software) to be developed as well as
to the production process have to be determined.
The organization must identify and take into ac-
count the product and process requirements known
from previous experience.
Special characteristics must be identified on the ba-
sis of the organization’s own requirements, cus-
tomer requirements, statutory and regulatory re-
quirements, manufacturing technology and charac-
teristics that arise from the purpose/use of the prod-
uct.
Customer requirements regarding the selection of
suppliers or primary materials must be docu-
mented.
In case of suppliers appointed by the customer (di-
rected suppliers), interface agreements are availa-
ble.
The customer’s requirements regarding the docu-
mentation and release of Free and Open Source
Software (FOSS) must be taken into account.
Product/process development
Requirements regarding the
interfaces between hardware
and software (products with
integrated/embedded soft-
ware)
Inquiry and contract docu-
ments, including requirement
specifications
Traceability concept
Ordering and inspection re-
quirements
Catalog of characteristics/ref-
erence samples
Product/process characteris-
tics, including characteristics
regarding functional safety
Purchasing conditions
Logistics requirements (pack-
aging, JIT, JIS, on consign-
ment)
Quality agreements, including
QM-specific requirements
Schedules
Portals/information platforms
on the Internet
Lessons Learned
Environmental aspects, recy-
cling requirements
Capability requirements
Requirements regarding re-
lease
Product development
Specifications, drawings
53
Process element P3: Product and process development planning
P3.1 Have the product/process-specific requirements been specified?
Minimum requirements relevant for assessment
Examples for implementation
Software specifications
Process development
Requirements regarding fa-
cilities, tools and inspection
equipment as well as work-
place and test station layout
Requirements regarding
handling, packaging, storage
and identification
Requirements for identifica-
tion, configuration and ensur-
ing correct installation of the
software
Copyright by VDA QMC