TUT-CP842-Oper guide-preliminary.pdf.pdf - 第38页
Changing the Production Program Follow the procedure below to change the production program. Note: Refer to the host computer operation manual for the procedure on how to transmit production programs. Procedure 1. Select…

Setting the Recovery Timing/Stop Mode at
Recovery Up
When Auto Recovery has been selected, recovery timing and stop mode at
recovery up must be specified.
Procedure
1. Select [Recovery] from the [Main] screen.
2. Select [Immediate] or [Delayed] from the [Recovery Timing]
section.
3. Select [Stop] or [Continuous] from the [Stop Mode at Recovery
Up] section.
Notes: 1. These settings are available when the recovery mode is set to
[Auto Recovery].
2. Refer to the CP-842E/842ME System Reference manual for
an explanation of recovery modes.
4. Press [Close] to return to the [Main] screen.
Chapter 3: Preparing for Production
Preliminary
3-7CP-842E/842ME Operator’s Guide

Changing the Production Program
Follow the procedure below to change the production program.
Note: Refer to the host computer operation manual for the procedure on how to
transmit production programs.
Procedure
1. Select [Program] from the [Main] screen.
2. Select the production program that is to be used in production
from the list of production program that display.
Note: Production Programs are stored on the hard disk in the machine. The
number of production programs that can be stored on the hard disk will
vary depending on the amount of available disk space. A list of all
production programs stored on the machine can be displayed by scrolling
down in the view window.
3. Press [OK] in the verification dialog box.
4. Press [Close] to return to the [Main] menu screen.
3.2 Production Programs
Chapter 3: Preparing for Production
Preliminary
3-8 CP-842E/842ME Operator’s Guide

Setting the Scheduled Production Quantity
Specify the number of panels that are scheduled to be produced using the
production program currently selected for use. The machine stops when the
scheduled production quantity has been produced.
Procedure
1. Select [Program] from the [Main] screen.
2. Press [Chg Scheduled Panels].
3. Input the scheduled production quantity using the numeric
keypad that appears.
4. Press [OK].
5. The numeric keypad will then disappear from the screen and the
scheduled production quantity that has been specified will be
enabled.
6. Press [Close] to return to the [Main] screen.
Note: If the scheduled production quantity is set to "0". Production continuous
indefinitely. The machine will continue to produce panels until the
operator quits production.
Chapter 3: Preparing for Production
Preliminary
3-9CP-842E/842ME Operator’s Guide