User Manual SIPLACE D3 4 Setting up and commissioning From software version SR.605.xx 07/2008 EN Edition 4.6 Commissioning the machine 251 4.6.3 A test run or st arting production → T est the line using the test PCB or a…

100%1 / 364
4 Setting up and commissioning User Manual SIPLACE D3
4.6 Commissioning the machine From software version SR.605.xx 07/2008 EN Edition
250
Wait until the operating pressure for the tape cutter has dropped to 0 MPa.
Wear robust protective gloves.
Do not reach inside the used tape channel.
4.5.2 Removing the separating plate
Loosen the two slotted screws (item 4 in Fig. 4.5 - 1, page 249)
Pull out the dividing plate.
4.6 Commissioning the machine
4.6.1 Commissioning the machine at the customer's premises
Check all modules for correct seating.
Wipe off the linear guide rails with a lint-free cloth before removing the shipping braces for the
X/Y axis. Do not use any solvent to do this (see Section 4.3.20
, page 245.
Switch on the machine and perform a reference run.
Copy the placement program onto the computer and test it.
Check the machine zero point after a period of warming up of 3 - 4 h.
Get the customer's operating personnel to equip the feeder modules according to the cus-
tomer's placement program.
Instruct them in handling the feeder modules using the JobGuide.
Check all customer-specific installed options (in particular software) for good functioning and
order any necessary spare parts using the order form or by fax.
4.6.2 Instructing the customer's personnel
Explain all customer-specific installed options, in particular software / software compatibility.
Explain programming of the program editors on the line computer / SIPLACE Pro.
Instruct the operators and line engineers in using the station software.
Explain about password protection.
Instruct the customer's personnel according to the user manual and preventive maintenance
manual.
User Manual SIPLACE D3 4 Setting up and commissioning
From software version SR.605.xx 07/2008 EN Edition 4.6 Commissioning the machine
251
4.6.3 A test run or starting production
Test the line using the test PCB or a PCB provided by the customer.
Record the customer product and performance data, prepare the data and document the data
in the installation report.
Secure the data and give the customer security copies.
4 Setting up and commissioning User Manual SIPLACE D3
4.6 Commissioning the machine From software version SR.605.xx 07/2008 EN Edition
252