3OM-1751 1-108 1303-001 7.3 "Upkeep" T ab Sheet When the [Upkeep] tab is pressed in the "MaintWM" window, the following tab sheet appears. [1] [2] [3] [4] [5] [6] [7] "Upkeep" window F3A88 T…

3OM-1751
1-1071303-001
7.2 "Oil" Tab Sheet
When the [Oil] tab is pressed in the "MaintWM" window, the following tab sheet
appears.
[1] [2] [3] [4]
"Oil" window F3A87
In this tab sheet the practice dates for the maintenance cycles (weekly, monthly,
every three months, every six months and every 365 days) of the oiling check are
displayed.
Reference
Refer to "1.3 Items for Periodic Maintenance" in Chapter 1, Volume 4, for the
details of oiling check.
[1] Cycle
For the standard maintenance cycle, "Weekly", "Monthly", "3-Monthly",
"6-Monthly" and "365" are set.
[2] Start Day
In these data boxes, the practice dates set up in the NT-100 system software,
are displayed.
[3] Warning
In these data boxes, "Enable" or "Disable" for the warning of the
maintenance timing set up in the NT-100 system software, is displayed.
[4] Days, Total Comp, End Day
When the setting is performed using the NT-100 system software, the
indications are updated such as "Days" to "0", "Total Comp" to "0" and "End
Day" to "Date of (Start Day + Cycle)".
When the value of "Days" (elapsed date) reaches the value of "Cycle", the
background color turns to pink.
7.2 "Oil" Tab Sheet
Graphic
Development

3OM-1751
1-1081303-001
7.3 "Upkeep" Tab Sheet
When the [Upkeep] tab is pressed in the "MaintWM" window, the following tab
sheet appears.
[1] [2] [3]
[4] [5] [6]
[7]
"Upkeep" window F3A88
The corresponding tab sheet enables the operator to display the setting status
and present status for the nozzle, lter #1 (head lter) and lter #2 (lter for air
supply).
[1] Group
In this section, the maintenance items of "Nozzle", "Filter #1" (head lter)
and "Filter #2" (air source lter) have been set.
[2] Start Day
In these data boxes, the practice dates set up in the NT-100 system software,
are displayed.
[3] Warning
In these data boxes, "Enable" or "Disable" for the warning of the
maintenance timing set up in the NT-100 system software, is displayed.
[4] Days
The total time period when the machine has been actually operated before
the practice date, is displayed using days and hours (24 hours).
When the total machine operation time period reaches the value of the
warning condition shown in [7], the background color turns to pink.
When the setting is performed using the NT-100 system software, the "Date"
display parameter is updated to "0".
7.3 "Upkeep" Tab Sheet
Graphic
Development

3OM-1751
1-1091303-001
[5] Total Comp
The total quantity of components actually picked up in the machine before
the practice date is displayed in these data boxes.
When the value of the total quantity of components reaches the value set in [7],
the background color turns to pink.
When the setting is performed using the NT-100 system software, the display
of "Total Comp" parameter is updated to "0".
[6] End Day
The end day is displayed as the date with the shortest period from the point
when the practice date is set referring to the current operation dates in these
data boxes.
[7] Term, Days, Total
For the "Upkeep", unlike the oiling check with specied maintenance
timing, maintenance with timing that depends on machine use condition is
performed.
As for conditions for issuing the maintenance warning message, the
parameters for the operation days and quantity of picked up components are
displayed.
When the value reaches either of the parameters for the above two set
conditions, the warning message is issued.
Note
The operation time period in "Days" data box is displayed as "1 day (24
hours)", "7 days (7
×
24 hours)", "1 month (30
×
24 hours)".
7.3 "Upkeep" Tab Sheet