00197369-02_AI_PPW_2te_Reihe_X-Serie-S_de_en.pdf - 第73页

Installation 3.1.4 Location 1 and 3 – Installing the "Support Option ASP Spe ed Flex Row 2 SP1/3" X4i S - Installing the NC Row 2 NC Row 2 - NC in Front of MTC 2/WPC PPW 2te Reihe - PPW vor MTC 2/WPC 73 Install…

100%1 / 104
Installation
X4i S - Installing the NC Row 2 3.1.3 Preparing the Compressed Air Connection
72 NC Row 2 - NC in Front of MTC 2/WPC PPW 2te Reihe - PPW vor MTC 2/WPC
3.1.3
3.1.3 Preparing the Compressed Air Connection
Preparing the Compressed Air Connection
To connect the second nozzle changer, you need to branch off the line to the nozzle station.
Use diagonal cutters to cut the supply line to the nozzle station about 5 cm behind the Y coupling.
3.1.4
3.1.4 Location 1 and 3 Installing the "Support Option ASP Speed Flex Row 2 SP1/3"
Location 1 and 3 – Installing the "Support Option ASP Speed Flex Row 2 SP1/3"
Parts required from "Support option ASP speed flex row 2" [03090225-xx]
NC option mount
Branched line to nozzle station
1. Y coupling for supplying the nozzle station and NC 2
2. 2A: Original line to nozzle station
2B: Branched line to nozzle station
3. Line to NC 1
4. Connection for line to NC2
Fit a Y coupling (1) to the original end of the line lead-
ing to the nozzle station (2A).
Fit the branch end of the line leading to the nozzle
station (2B) into the corresponding connection on the
Y coupling.
Plug the line leading to NC2 into the connection at (4)
when installing the NC2.
Quantity Designation Item number
2 NC option mount 03005337-xx
2 ISO4762 - M5 x 14-A2-70 03043120-xx
At locations 1 and 3 you need the NC option mount
[03005337-xx] with prefitted shim plates for the left and
right sides.
Installation
3.1.4 Location 1 and 3 – Installing the "Support Option ASP Speed Flex Row 2 SP1/3" X4i S - Installing the NC Row 2
NC Row 2 - NC in Front of MTC 2/WPC PPW 2te Reihe - PPW vor MTC 2/WPC 73
Installation
Attaching the mount – example of right side
Fit the mount for the second row from the left, onto
the mount for the first row.
Press the mount down firmly so that the two align-
ment pins (1) and (2) are completely inserted into the
relevant holes on the front mount.
Screwing the mount into place – example of right side
Screw the mount for the second row into place from
the left side (1).
Installation
X4i S - Installing the NC Row 2 3.1.4 Location 1 and 3 – Installing the "Support Option ASP Speed Flex Row 2
74 NC Row 2 - NC in Front of MTC 2/WPC PPW 2te Reihe - PPW vor MTC 2/WPC
For configurations without Smart Pin Support, continue with section "3.1.8 Checking the Height"
[➙80].
For configurations with Smart Pin Support, continue with section "3.1.7 Inserting the NC ASP Sup-
port Plate" [ ➙ 78].
See also
3.1.5 Location 2 and 4 – Installing the "Support Option ASP Speed Flex Row 2 SP1/3" [ ➙ 75]
NC option mount installed (left side)
1. Alignment pins
2. Fastening screw
NC option mount installed (right side)
1. Alignment pins
2. Fastening screw