00198711-01_UM_X-Serie-S_EN.pdf - 第227页

Instruction manual SIPLACE X-Seri es S 4 Setting up and commissioning From software version 713.0 Edition 11/2019 4 .6 Commissioning the placement machine 227 4.6.2.1 Performing initial calibration  Click on "Servi…

100%1 / 360
4 Setting up and commissioning Instruction manual SIPLACE X-Series S
4.6 Commissioning the placement machine From software version 713.0 Edition 11/2019
226
4.6 Commissioning the placement machine
4.6.1 Commissioning the placement machine at the customer's premises
Check all modules for correct seating.
Remove the shipping braces (see section 4.3.9, page 4.3.9).
Wipe the linear guide rails of the X/Y axis with a lint-free cloth. Do not use any solvents (see
section 4.3.10
, page 222).
Connect the power and compressed air supplies. Make sure that the incoming leads and ca-
bles can not be tripped over. If possible, run the incoming cables under the placement ma-
chine.
Switch the placement machine on and check the function of the safety features such as the
EMERGENCY STOP button, position switch for covers and the component trolley.
Perform a reference run.
Perform initial calibration of the placement machine (see section 4.6.2.1, page 227).
Load a recipe in the computer and test it.
Check the placement machine zero point after a period of warming up of 3 - 4 h.
Get the customer's operating personnel to equip the feeder modules according to the cus-
tomer's placement program.
Instruct them in handling the feeder modules using the JobGuide.
4.6.2 Checking and setting the protective cover switch
Check the function of the protective cover switch (see 2.4.1 on page 63).
Adjust the protective cover switch if necessary (see service manual).
Instruction manual SIPLACE X-Series S 4 Setting up and commissioning
From software version 713.0 Edition 11/2019 4.6 Commissioning the placement machine
227
4.6.2.1 Performing initial calibration
Click on "Service Tools" in the toolbar.
Click on the Automatic calibration button.
4
Fig. 4.6 - 1 Service tools => automatic calibration (example)
Select Selection => Gantry axis calibration (1).
(1)
4 Setting up and commissioning Instruction manual SIPLACE X-Series S
4.6 Commissioning the placement machine From software version 713.0 Edition 11/2019
228
4
Fig. 4.6 - 2 Service tools => automatic calibration => calibrating the gantry axes (example)
The following calibration steps are enabled:
1. Travel range
3. System identification
4. Parameterization X axis
Click on Next (1).
The calibration must be completed without errors.
(1)