00191369-02.pdf - 第327页
User Manual HS-50 7 What should you do ... Software V ersion SR.501.xx 12/99 Issue US 7.2 Switching off the SIPLAC E line 327 t I I t 7.2.2 Switching off the st ations Procee d as foll ows to swi tch off the s tation: 7 …

7 What should you do ... User Manual HS-50
7.2 Switching off the SIPLACE line Software Version SR.501.xx 12/99 Issue US
326
t IIt
7.2 Switching off the SIPLACE line
ATTENTION
Before you switch off the line, ALWAYS make sure that: 7
– All placement operations on the stations are completed.
– The Z-axis of all placement heads are in the top end position.
– None of the placement heads still contain components.
– All gantries have moved into the standby position.
– The station computers have been properly shut down.
7.2.1 Switching off the line computer
CAUTION
NEVER just switch off the line computer on the power switch (of the UPS).
ALWAYS shut down the operating system of the line computer with "Shutdown". Otherwise you
will almost certainly lose a lot of data and may need to reinstall the line computer software. 7
Å Position the mouse at the right or lower edge of the screen.
The cursor will change into a cross.
Å Press and hold down the left mouse button. The main menu appears.
Å Move the mouse cursor onto the ’Shutdown’ menu item and then release the mouse button.
The following dialog box appears on screen:
Å Click on yes. The dialog box closes and the
operating system
shuts down. This operation takes
around 1 minute. The following then appears:
Å Switch off the UPS.
really shutdown?
yes no
** Safe to Power Off **
-or-
** Press Any Key to Reboot **

User Manual HS-50 7 What should you do ...
Software Version SR.501.xx 12/99 Issue US 7.2 Switching off the SIPLACE line
327
t IIt
7.2.2 Switching off the stations
Proceed as follows to switch off the station: 7
Å Terminate all placement operations.
Å Check to make sure that the z-axes of all placement heads are in the upper end position.
Å Check to see if there are still components in the placement heads and remove any components
found.
Å If necessary, move all gantries to the standby position with the help of the corresponding gantry
functions (see chapter 5
, section 5.2.2.1).
NOTE
All gantries are normally moved to the standby position automatically. 7
Å Now switch off the station on the main switch.
7.2.3 Starting stations that remain switched on after the line computer has been
shut down
If stations remain switched on after the line computer has been shut down and the line computer
is then restarted, the computer will not automatically establish connections with those stations.
The following error messages may appear on the line computer monitor: 7
– No correct connection between line computer and station
– The line computer was shut down and restarted, so the station must also be shut down and
restarted.
7
There are two ways of re-establishing the connection between the line computer and station after
the line computer has been shut down: 7
1st option 7
Å Disable the conveyor interface at the stations from the ‘Machine options’ menu.
Å Run all the PCB feeders on the line until they are empty.
Å Switch the stations off and on again.
The stations will establish connections with the line computer.
Å Press the Start button when prompted. The reference point run will then be carried out.
Å Continue placement.

7 What should you do ... User Manual HS-50
7.3 Changing jobs Software Version SR.501.xx 12/99 Issue US
328
t IIt
2nd option 7
Å Select the ‘Line engineer’ access level (password required) from the ‘Options’ menu.
Å Select the ‘Stand-alone’ option from the ‘Operating mode’ menu.
The PCB conveyor for the station will run on until empty.
Å Wait until you are prompted to press the Start button.
Å Select ‘Line computer’ from the ‘Operating mode’ option in the ‘Options’ menu.
The station will automatically establish a connection with the line computer.
Å Press the Start button.
The reference point run will then be carried out.
Å Set the access level back to ‘Operator’.
Å Continue placement.
7.3 Changing jobs
Å Interrupt the job defined for the station on the line computer using the function (Interrupt).
Å Enter the new job on the line computer using the function (Schedule).
Å Check the width of the conveyor belt.
Å Check the position of the magnetic supports and make sure that they cannot collide with com-
ponents on the bottom of the PCB.
Å Carry out the set-up check.
Make sure that the feeder modules are equipped with the correct components and that the
feeder modules are at the correct locations.
Å Check the nozzle configuration in the nozzle changer.
If no nozzle changer is installed, then you must change the nozzles manually.
NOTE
If you change the nozzle manually, ALWAYS make sure that you are using the correct nozzle
type and that the nozzle is seated correctly on the spindle. (The plunger pin must click into
place in the notch slot of the nozzle).
If you have not inserted a nozzle or have used the wrong nozzle type, then the station com-
puter program will prompt you to move the placement head to the service position and change
the nozzle. This error message will also appear if you have not inserted the nozzle correctly.
If you insert the wrong nozzle or use the wrong nozzle type again, then the gantry will move to
the service position once more after the reference sequence. The station computer program