4OM-1733 1-4-42 4.8.6 Y -axis Cable Fixing Location Check Cycle : Every 6 Months (Required Time : 1 minute) Y-Axis Cable Fixing Location Fig. 4A4-53 Procedure Check visually for any abnormality such as cracks. 4.8.7 Y -a…

100%1 / 153
4OM-1733
1-4-41
4.8.5 Y-axis Cable Side Cleaning and Oiling
Cycle : Every 6 Months (Required Time : 3 minutes)
Grease : BARRIERTA IEL/V
Y-Axis Cable Side
Fig. 4A4-52
Procedure
(1) Wipe off old grease with an oiled rag.
(2) Apply new grease by hand or with a brush.
Notice
Take ample care not to leave any waste threads after cleaning.
1211-002
4.8 X/Y Beam Section
4OM-1733
1-4-42
4.8.6 Y-axis Cable Fixing Location Check
Cycle : Every 6 Months (Required Time : 1 minute)
Y-Axis Cable Fixing Location
Fig. 4A4-53
Procedure
Check visually for any abnormality such as cracks.
4.8.7 Y-axis Linear Encoder Scale-Tape Cleaning
Cycle : Every 6 Months (Required Time : 5 minutes)
Linear Encoder Scale-Tape
Fig. 4A4-54
Procedure
When it is very dirty, clean it using a cloth soaked in alcohol.
1211-002
4.8 X/Y Beam Section
4OM-1733
1-4-43
4.9 PCB Positioning Section
Ball Screws (3 locations)
Every 3 Months Cleaning and Lubrication
(DAPHNE EPONEX GREASE No. 1)
Required Time: 10 minutes
Upper Surface of Backup Table
Every Week Cleaning
Required Time: 2 minutes
Fig. 4A4-55
The nipple are located on the lower side
of the backup table.
Ball Screws (3 locations)
Every 3 Months Cleaning and Lubrication
(DAPHNE EPONEX GREASE No. 1)
Required Time: 10 minutes
Ball Screw Spline (Four places to nipple)
Every 6 Months Cleaning and Lubrication
(DAPHNE EPONEX GREASE No. 1)
Required Time: 10 minutes
Upper Surface of Backup Table
Every Week Cleaning
Required Time: 2 minutes
Note
Fig. 4A4-55-1 Y510mm Single Transfer Unit (Option)
Note
This optional unit can be selected when the system is delivered from the factory.
1403-004
4.9 PCB Positioning Section