4M184002w_F8S.pdf - 第76页

4OM-1840 1-4-1 1604-001 4. Inspection, Cleaning, and Lubrication Spots 4. Inspection, Cleaning, and Lubrication Spots The following describes about the maintenance tasks required for each individual units. Reference Refe…

100%1 / 315
4OM-1840
1-3-21604-001
Bank Feeder Change Cart
XY-Beam
(X-Axis Beam)
XY-Beam Section (Y-Axis Beam)
Component
Recognition Camera
Placemant Head,
PEC Recognition Section
PCB Transfer
Conveyor Unit
Rejected Component Box
Nozzle Stocker Section
Fig. 4A3-2
3.1 Whole View
4OM-1840
1-4-11604-001
4. Inspection, Cleaning, and Lubrication Spots
4. Inspection, Cleaning, and Lubrication Spots
The following describes about the maintenance tasks required for each individual
units.
Reference
Refer to "2. Maintenance Check List" in "Chapter 1" for the maintenance items

4.1 Air Source
Air Blowing Pressure
Every Day Inspection
Required Time: 1 minute
Main Air Pressure
Every Day Inspection
Required Time: 1 minute
Drain
Drain
Every Week Cleaning
Required Time: 5 minutes
Fig. 4A4-1
4OM-1840
1-4-21604-001
4.1.1 Air Blow Pressure Check
Cycle : Every Day (Required Time : 1 minute)
Air Blowing Pressure
Fig. 4A4-2
Procedure
Check to see that the pressure gauge reads the initial setting (0.05 MPa
(0.5 kgf/cm
2
)). Do not change the pressure unless necessary.
Notice
The pressure is factory-adjusted upon shipment of the machine.
4.1 Air Source