00198382-03_UM_SIPLACE-CA4-V2_EN.pdf - 第192页

4 Setting up and commissioning Instruction manual SIPLACE CA4 V2 4.6 Commissioning the placement m achine From software version 713.0 Edition 12/2019 192

100%1 / 322
Instruction manual SIPLACE CA4 V2 4 Setting up and commissioning
From software version 713.0 Edition 12/2019 4.6 Commissioning the placement machine
191
4.6.4 A test run or starting production
Test the line using the test PCB or a PCB provided by the customer.
Record the customer product and performance data, prepare the data and document the data
in the installation report.
Secure the data and give the customer security copies.
4 Setting up and commissioning Instruction manual SIPLACE CA4 V2
4.6 Commissioning the placement machine From software version 713.0 Edition 12/2019
192
Instruction manual SIPLACE CA4 V2 5 Tasks at the placement machine
From software version 713.0 Edition 12/2019 5.1 Staff profiles
193
5 Tasks at the placement machine
This chapter contains a number of subjects that are intended to help you during your daily work
on a SIPLACE line. For example, you are provided with preventative measures that you can take
to minimize the down time on the machine to obtain the highest possible level of efficiency for the
SIPLACE line during production.
5.1 Staff profiles
5
Certain functions or menus may only be executed or can only accessed by specially trained per-
sonnel. A differentiation is made between the following operator levels:
Production
Advanced production
Service (customer)
The operator levels "Advanced production" and "Service (customer)" can be password protected.
PLEASE NOTE
Correct usage with qualified personnel
Incorrect usage poses a risk to life and limb and a risk of damage to equipment.
Only appropriately qualified personnel may put the placement machine into opera-
tion, operate it or perform work to the placement machine. You will find further infor-
mation about this in section 1.2.6
, page 23.
Evidence of these qualifications must be obtained in training or instructions of per-
sonnel. These instructions must be given by personnel trained and authorized by SI-
PLACE. For an overview of the training courses, refer to section 1.3
, page 25.