0019797 3 - 10 / 02 , 2016 Option Air Dryer SIPLACE Mat. Towe r St ora ge Serv ice Manual © ASM 11 -3 11.1.4 Exchange steps Cover removal Remove the foll owing covers t o retrofit the air dryer: • Tall co ver left side o…

Option Air Dryer 00197973-10 / 02 , 2016
11-2 © ASM SIPLACE Mat. Tower Storage Service Manual
Spare parts:
03124552
-01, RETROFIT Air Dryer including:
• Membrane dryer
• Air Flow Limiter
• 4mm, 8mm and 15mm hose
• Possibly: Connection panel (if old panel
version without holes mounted)
• Through hole connectors for air
supplies/exhaustion
• Magnetic valve
• Control cable for magnetic valve
• Drain cover
• Sealing belts
• Humidity sensor
Time needed
Schedule around 2 hours for this task.
11.1.3 Prerequisites
For a safe and efficient maintenance, the following prerequisites have to be fulfilled:
Personnel:
• Any work with or at the equipment must be carried out by skilled and
trained personnel in accordance with the locally applicable
regulations.
• Inform all involved persons regarding the currently running
maintenance works.
Machine loading:
•
NO item must be unloaded.
Machine operating
condition:
• Shut down
Main electrical
power:
• Equipment disconnected from power supply system. The Main Switch
(switched off) locked by means of a padlock to secure the main switch
against unintentional switching on.
Compressed air /
Nitrogen (if used):
• Equipment disconnected from compressed air or nitrogen supply.
Access:
• Open the left side door of the machine, where the electrical unit and
the air dryer is located.

00197973-10 / 02 , 2016 Option Air Dryer
SIPLACE Mat. Tower Storage Service Manual © ASM 11-3
11.1.4 Exchange steps
Cover removal
Remove the foll
owing covers to retrofit the air
dryer:
• Tall cover left side of the portal
• Small cover below the portal
• Open both maintenance doors
Step 1
Position of the connection plate is below the
portal.
It might be required to remove the few lower
shelves to gain comfortable access to the plate.

Option Air Dryer 00197973-10 / 02 , 2016
11-4 © ASM SIPLACE Mat. Tower Storage Service Manual
• NT-1004898, 8mm bulkhead union
• NT-1004897, 4mm bulkhead union
• 69.999.00021, 15mm elbow union
• 69.999.00022, 15mm bulkhead union
• 40.050.06725, silencer
Prepare the required parts. There are two
possibilities in this case:
• If the connection plate on this storage unit is
a new one, all parts will be loose.
• If the new connection plate is in the
delivery, all parts are already mounted and
the following intermediate steps can be
skipped
. Just replace the new plate with the
old one and go to step 2.
Wrap Teflon tape around the thread of the
15mm bulkhead union (approx. 5 times).
Remove all three caps covering the holes by
pressing them through.