07/2002 Editio n Student G uide HS -50 Advanc ed II 14 Conveyor System 42 Fig. 14.3.8 Removing the M otor of the Width Adjust ment Syst em or the Drive of the Width Adjust . System ( Complete) Key to Fig. 14.3 .8 ➠ In th…

100%1 / 431
Student Guide HS-50 Advanced II 07/2002 Edition
14 Conveyor System
41
 ,QVWDOOLQJD7RRWKHG%HOWIRUWKH:LGWK$GMXVWPHQW6\VWHP6KRUW
CAUTION O
The new toothed belt is not to be stretched or kinked. 14
Install the new drive toothed belt in the reverse order to that described above for the removal.
Bolt the motor to the drive housing.
Check: The HQWLUHZLGWKof the toothed belt must be engaged on the synchronizing disk
Remove all tools, etc., from the working area of the machine.
Make certain that the transmission lever on the lifting table motor mount is folded onto the lift-
ing curve (see Fig. 14.3.5, illustration bottom left).
Re-install the lifting table as described in section 14.3.8.2.
Carry out the appropriate )LQDOVWHSVLQFOXGLQJWKHIXQFWLRQFKHFN(see section 14.4).
During the function check, move the conveyor to its maximum and minimum width.
 ([FKDQJLQJWKH6WHSSLQJ0RWRURIWKH:LGWK$GMXVWPHQW6\VWHP
CAUTION O
During the following removal and installation of the motor, the toothed belt for the drive of the width
adjustment system are not to be stretched or kinked. 14
 5HPRYLQJWKH6WHSSLQJ0RWRUIRUWKH:LGWK$GMXVWPHQW6\VWHP
For removal, proceed as described in section 14.3.12.1.
For electrical isolation, proceed as follows:
Lift the cover off the relevant cable duct placed parallel to the conveyor assembly adjust-
ment plate.
Carefully remove the appropriate cable ties.
07/2002 Edition Student Guide HS-50 Advanced II
14 Conveyor System
42
Fig. 14.3.8 Removing the Motor of the Width Adjustment System or the Drive of the Width Adjust. System (Complete)
Key to Fig. 14.3.8
In the cable duct, disconnect the plug-and-socket connection for this motor of the width adjust-
ment system (;RU;: see circuit diagram for "6/,2PRGXOHRQ3&%FRQYH\RU
or RQ3&%FRQYH\RU.
NOTE:
If you have discovered a break in the motor cable during a continuity check and this break is up-
stream of the plug-and-socket connection, the motor cable must be run on a weaving course as
far as the "conveyor control PCB 1" / "... PCB 2" (see ) and unplugged at the connector X3 of
the corresponding "conveyor control" (see above-mentioned circuit diagram). This may be some-
what complicated due to the routing of the cable inside the machine base.
You may wish to contact Siemens SMD Service regarding this work. 14
Pull the motor out of the drive housing.
1) Drive for width adj. system (complete)
(incl. Pos. 3 and 4 or 5 and 6)
2) Drive housing for width adj. system for con-
veyor 1 and 2
3) Motor width adj. system conveyor 1 4) Cable for motor width adj. system conv. 1
5) Motor width adj. system conveyor 2 6) Cable for width adj. system conveyor 2
7) Screws to fasten the motor:
4 hexagonal socket head cap screws M 3
8) 2 hexagonal socket head cap screws
M 6 x 80
Student Guide HS-50 Advanced II 07/2002 Edition
14 Conveyor System
43
 ,QVWDOOLQJWKH6WHSSLQJ0RWRUIRUWKH:LGWK$GMXVWPHQW6\VWHP
CAUTION O
The new toothed belt is not to be stretched or kinked. 14
Install the new stepping motor in the reverse order to that described above for the removal. Bolt
the motor to the drive housing.
Check: The HQWLUHZLGWKof the toothed belt must be engaged on the synchronizing disk
Remove all tools, etc., from the working area of the machine.
Make certain that the transmission lever on the lifting table motor mount is folded onto the lift-
ing curve (see Fig. 14.3.5, illustration bottom left).
Re-install the lifting table as described in section 14.3.8.2.
Carry out the appropriate )LQDOVWHSVLQFOXGLQJWKHIXQFWLRQFKHFN(see section 14.4).
During the function check, move the conveyor to its maximum and minimum width.
 ([FKDQJLQJWKH'ULYHIRUWKH:LGWK$GMXVWPHQW6\VWHP&RPSOHWH
NOTE:
Exchange the entire unit "Drive for width adjustment system", e.g., in case of a fault in the ball
bearing/syconronizing disks and motor. 14
 ([FKDQJLQJWKH'ULYHIRUWKH:LGWK$GMXVWPHQW6\VWHP&RPSOHWH
Remove the lifting table as described in section 14.3.8.1.
Relieve the stress on the large toothed belt for the width adjustment system as described
above in section 14.3.12.1 .
Take the large toothed belt off the sprocket wheels of the drive unit.
Detach the plug-and-socket connection of the motor of the width adjustment system LQWKHFD
EOHGXFWas described above in section 14.3.13.1.
Undo and remove the screws fastening the drive housing to the assembly base plate (2 hex-
agonal socket head cap screws M6: see Fig. 14.3.8 -> 8). Lift the "Drive for the width adjust-
ment system" out.
 ,QVWDOOLQJWKH'ULYHIRUWKH:LGWK$GMXVWPHQW6\VWHP&RPSOHWH
Install the new "Drive for the width adjustment system" in the reverse order to that following
during removal.
Place the large toothed belt for the width adjustment system on the deflection pulleys.
Check: The HQWLUHZLGWKof the toothed belt must be engaged on the two outside synchronizing
disks (on the pedestal) and must be in contact with the circumference of the deflection pulleys.