EUKYX-199-2100_G5S2_Instruction_Vol2_E.pdf - 第152页
EUKYX 2-39 199-2100 3.4 Control (D02 _05) DN Positioni ng 1 , Positi oning 2 MOVE The PCB movi ng down operati on for posi tion ing is sel ecte d from "St andard" or "V alue Set" . Normally , " S…

EUKYX
2-38199-2100
3.4 Control
(D02_01)
PCB detection off DLY
It is not currently used.
(D02_02)
PCB locate SET
Common : When selected, the PCB positioning is set commonly to the machines in the line.
Individual : When selected, the PCB positioning is set individually for each machine in the
line.
(D02_03)
PCB locate Sequence
The PCB positioning mode is set in this text box.
Standard : The positioning is performed with both backup base and Z clamp.
Change Z clamp timing : The positioning with Z clamp is performed
after completing the positioning with the backup base.
Vacuum support + Z clamp: The positioning is performed with the vacuum jig and Z clamp.
Only vacuum support : The positioning is performed with the vacuum jig only.
(D02_04)
UP
Positioning 1, Positioning 2
MOVE
The PCB moving up operation for positioning is selected from "Standard" or "Value Set".
Normally, "Standard" is selected.
Standard : When selected, the PCB is moved up for positioning based on the standard value
set in the machine.
Low Speed 1 : When selected, the operation speed is one step lower than the standard value.
Low Speed 2 : When selected, the operation speed is two step lower than the standard value.
Low Speed 3 : When selected, the operation speed is three step lower than the standard value.
Low Speed 4 : When selected, the operation speed is four step lower than the standard value.
Value Set : When selected, the speed value can be set freely.
1st speed DCLR SET
The backup base operation speed reduction rate is set in this text box.
This value is reflected on the first operation in the 2-stage operation in the PCB positioning, and
second operation in the 2-stage operation in the PCB releasing.
2nd speed DCLR SET
The backup base operation speed reduction rate is set in this text box.
This value is reflected on the second operation in the 2-stage operation in the PCB positioning, and
first operation in the 2-stage operation in the PCB releasing.
Z Clamp
Opr. waiting time: The Z-clamp operation WAIT time is set in this text box.
Opr. ST DLY timer: The time period from the backup base moving up start to Z-clamp moving up
start, is set in this text box
.

EUKYX
2-39199-2100
3.4 Control
(D02_05)
DN
Positioning 1, Positioning 2
MOVE
The PCB moving down operation for positioning is selected from "Standard" or "Value Set".
Normally, "Standard" is selected.
Standard : When selected, the PCB is moved up for positioning based on the standard value
set in the machine.
Low Speed 1 : When selected, the operation speed is one step lower than the standard value.
Low Speed 2 : When selected, the operation speed is two step lower than the standard value.
Low Speed 3 : When selected, the operation speed is three step lower than the standard value.
Low Speed 4 : When selected, the operation speed is four step lower than the standard value.
Value Set : When selected, the speed value can be set freely.
1st speed DCLR SET
The backup base operation speed reduction rate is set in this text box This value is reflected on the
first operation in the 2-stage operation in the PCB positioning, and second operation in the 2-stage
operation in the PCB releasing.
2nd speed DCLR SET
The backup base operation speed reduction rate is set in this text box.
This value is reflected on the second operation in the 2-stage operation in the PCB positioning, and
first operation in the 2-stage operation in the PCB releasing.
Backup axis DN start DLY
The time period for the Z-clamp releasing operation completion after the component placement
completion, is set in this text box. After this operation is completed, the backup base starts moving
down.
(D02_06)
SW POSN of 1st / 2nd
The change position between the “First Speed” and “Second Speed” is set in this data box.
(D02_07)
Replace vacuum sensor
The sensor to be used for vacuum pick-up is selected in this data box.
This function is used when the vacuum judgment threshold value is to be changed.
Sensor #1 : When selected, the vacuum pick-up is performed using the sensor #1.
Sensor #2 : When selected, the vacuum pick-up is performed using the sensor #2.
(D02_08)
PCB position of contact
The offset from the transfer position (moving up first stage/moving down first stage target position)
is setup. The value for carrier thickness, etc., is input as upper direction value (plus value).

EUKYX
2-40199-2100
3.4 Control
(D02_09)
UP
MOVE
“Standard” or “Value Designation” is selected for the PCB positioning moving up operation.
Normally, “Standard” is selected.
Standard : The operation is performed based on the standard values set in
the machine.
Value Designation : For the operation procedure, the selected values can be setup.
1st speed DCLR SET
The speed reduction rate for the backup base first stage operation in the PCB positioning, is setup
in this data box. This value is reflected on the speed and acceleration.
2nd speed DCLR SET
The speed reduction rate for the backup base second stage operation in the PCB positioning, is
setup in this data box. This value is reflected on the speed and acceleration.
Vac. Ctrl. delayed starts
The time period from the backup base first stage operation start-up in the PCB positioning to the
vacuum pick-up turning ON, is set in this data box.
Vac. Wtg. Timer
The time period from the backup base first stage operation start-up in the PCB positioning to the
second stage operation start-up, is set in this data box.
Z clamp waiting time
The time period for judging for the Z-Clamp Moving-up Completion in the PCB positioning, is set in
this data box.
(D02_10)
DN
MOVE
"Standard" or "Value Designation" is selected for the PCB positioning moving -down operation.
Standard : The operation is performed based on the standard values set in the
machine.
Value Designation: For the operation procedure, the selected values can be setup.
1st speed DCLR SET
The speed reduction rate for the backup base first stage operation in the PCB positioning clearance
operation, is setup in this data box. This value is reflected on the speed and acceleration.
2nd speed DCLR SET
The speed reduction rate for the backup base second stage operation in the PCB positioning
clearance operation, is setup in this data box. This value is reflected on the speed and acceleration.
Vac. Ctrl. delayed starts
The time period from the operation start-up in the PCB positioning clearance operation to the
vacuum pick-up turning OFF, is set in this data box.
Vac. Wtg. Timer
The time period from the first stage operation completion to the second stage operation start-up in
the PCB positioning clearance operation, is set in this data box.
Damaged Vac. Wtg. time
The time period of the vacuum breakage ON operation in the PCB positioning clearance operation,
is set in this data box.
Backup axis DN start DLY
The time period until the backup base first stage operation start-up in the PCB positioning clearance
operation, is set in this data box.