CM602all_EJM8AESM_Service Manual.pdf - 第177页
Maintenance Adjustment Main Body Beam EJM8A-E-SMA040111-A01-00 Page4-1-11-3

Maintenance Adjustment Main Body Beam
EJM8A-E-SMA040111-A01-00
Page4-1-11-2

Maintenance Adjustment Main Body Beam
EJM8A-E-SMA040111-A01-00
Page4-1-11-3

Maintenance Adjustment Main Body Beam
This section describes the procedures for adjusting the clearance between the cutter blades.
・Tools
Feeler gauge
Allen key 4 mm
Hammer
・Jig
FM-1044
Cutter blade installing jig
4-1-12 Adjusting the Clearance between the Cutter Blades
Danger! Do not touch the cutter blades.
Be very careful when removing the cutter unit; it is heavy.
Assembly
Adjustment
45min.
Teaching
min.
Total Time Weight of
Part
Removal
Disassembly
45min.
90min.
40kgs
Caution
Dange
r
Warning
EJM8A-E-SMA040112-A01-00
Page 4-1-12-1