Operating Manual Reference Figure CP-45/55 Operation Process Modifying this option may have no effect on the array of nozzle or feeder. ^ <Time(sec)> Edit Box Area This area is to input time taking when executing i…

Operating Manual Reference Figure
CP-45/55 Operation Process
Select the <Normal> for general
PCB, and select <Strict> for PCB
requiring the application of strict
rule. <Search Depth> option is to
determine the execution method
of mounting order algorithm.
This is caused that it takes
too much time to execute the
optimizer generally for optimizing
the mounting order. Also, the
optimizer execution time
increases as the numbers of
mounting point increase. If you
selecting the <Quick>, you can
determine the mounting order
rapidly. However, in general, the
finial work efficiency is inferior
to a case which selects the
<Deep>. To increase the work
efficiency regardless of
optimizer execution time, select
the <Deep>.

Operating Manual Reference Figure
CP-45/55 Operation Process
Modifying this option may
have no effect on the array of
nozzle or feeder.
^ <Time(sec)> Edit Box Area
This area is to input time taking
when executing individual
movement on the unit and can be
used for calculating the work
time in the Optimizer. Also,
values of Tray Y and Tray Z
may have an effect on the
determination of work order.
Thus, be sure to input the value
close to the actual to increase
the work efficiency and take the
accurate prediction value of work
time.
# ANC : Time(sec) to be taken
for 1 time nozzle replacement
# Fiducial : Time(sec) to be taken
for Fiducial mark acknowledge
# Vision: Time(sec) to be taken
for acknowledging Vision part
in Fixed Camera

Operating Manual Reference Figure
CP-45/55 Operation Process
# Tray Y: Time(sec) to be taken
when Tray of Multi-Tray
Feeder moves to Y direction.
#Tray Z: Time(sec) to be taken
when Tray of Multi-Tray
Feeder moves to Z direction.
If execution of Optimizer is
completed, a dialogue box will be
shown as follows. This dialogue box
displays various results so that the
optimized status can be shown at
a glance. If clicking the <Accept>
button, this dialogue box will be
closed, the Optimizer will be finished,
and this result will be reflected to
the step program of MMI. If clicking
the <Reject> button, the result will
not be reflected to the step program
of MMI and the Optimizer option
dialogue box will be open again.
If necessary, readjust the Optimizer
option and execute it again.
* Optimization Result