1.1 Maintenance Procedure Be sure to observe the following procedures when carrying out the maintenance. 1. Check that all works on a machine are completed. 2. Turn off the main power switch prior to maintenance. 3. Meas…

100%1 / 208
ٛ Daily Inspection
* Maintenance
* Feeder Calibration Method
Maintenance
CP-45/55 Operation Process
1.1 Maintenance Procedure
Be sure to observe the following procedures when carrying out the maintenance.
1. Check that all works on a machine are completed.
2. Turn off the main power switch prior to maintenance.
3. Measurement and repair should be carried out only by the qualified personnel.
4. Care is to be taken for ensuring that S/W of a system can not be turned on again. Failure to
observe this may cause death or serious injury to personnel when contacting with a live part.
5. Carry out the maintenance in accordance with the Daily Inspection List.
Observe the following procedures for proper operation of a system after completion of maintenance.
1. Look around for obstacles where the maintenance is carried out, and remove that if required.
2. Check that all parts are assembled properly.
3. Turn on the main power switch of a system.
4.
Error! It fails to find out the reference copy. Error! It fails to find out the reference copy.
Turn on the power of a system in accordance with (
Error! The leaves of a book fails to be defined.
page).
Check that the system runs properly.
Warning
@ Failing to turn off the power switch may cause serious
injury to personnel. Be sure to turn off the power s witch
when inspecting t he system.