2-9 2 Basic operations 2.1 Inspecting before operation T he table below shows chec kpoints you should make before turning the power on. e w W ARNING AL W A YS BE SURE TO PRESS THE EMERGENCY STOP BUTTON BEFORE ST ARTING T…

2-8
2
Basic operations
2. Starting and stopping the machine
This section explains routine procedures for starting and turning off the machine according to the flow charts
below.
Starting and turning off the machine
Program is loaded.
Return-to-origin dialog box appears.
Operation and production
Confirmation dialog box appears.
Move-to-origin dialog box appears.
Setup screen appears.
Return axes to origins
Turn on power switch
Check before operation
Perform return-to-origin
Press [Off] button on operation screen
Press emergency stop button
Turn off machine power switch
Specify operator
Starting the
machine
Turning off the
machine
63203-L3-00

2-9
2
Basic operations
2.1 Inspecting before operation
The table below shows checkpoints you should make before turning the power on.
e
w
WARNING
ALWAYS BE SURE TO PRESS THE EMERGENCY STOP BUTTON BEFORE STARTING THE INSPECTION.
n
Checkpoints before operation
Checkpoints Check items Refer to
Conveyor unit
Check that no foreign matter or debris is on the
conveyor unit.
Check that the push-up jigs or matrix pins are not set
in areas wider than the board width to be produced.
Check that no matrix pins come loose from the push-
up table.
"4. Conveyor unit" in Chapter 1
Mask camera
Check that no foreign matter is sticking to the mask
camera.
Extended exit
conveyor (option)
Check that no board remains on the conveyor.
Check that no solder and debris adheres to the
conveyor.
Check that the cover is closed.
Squeegee
Check that the squeegee knobs are securely
tightened.
Check that the squeegee scrapers have no
scratches, nicks and wear.
Check that no solder and grit are adhering to the
squeegee.
"3. Printing section" in Chapter 1
Cleaning unit
Check that the cleaner gauze roll is set correctly.
Check that the tank is refilled with cleaning alcohol
sufficiently.
"5. Cleaning unit" in Chapter 1
Mask frame
stopper positions
Check that the mask frame stopper positions are
correct.
"2. Compatible masks" in Appendix
Upper door
(safety door),
panels
Check that the upper door and panels are all closed.
Solder
Check that solder has returned to room temperature
and is well agitated and rolled.
Solder manufacturer's instruction
manual

2-10
2
Basic operations
2.2 Starting the machine
1
Turn the power switch ON.
Turn on the power switch at the front lower right of the machine, by turning it to the right. The
initialization screen appears to start loading the program needed for machine operation.
ON
OFF
Power switch
63204-L3-00
2
Perform return-to-origin.
The return-to-origin dialog box appears after initialization. Follow the instructions on the screen to start
return-to-origin operation. The main screen then appears when return-to-origin is complete.
Return-to-origin dialog box
Press [Yes] to start return-to-origin.
64203-L3-00
c
CAUTION
Before starting return-to-origin, always make sure no squeegee is attached to the squeegee head.