User Manual SIPLACE CA 5 Tasks on the Machine Edition 08/2011 EN 5.3 Changing Shifts 343 5.3 Changing Shif t s  S plice the tapes early . The feeder modules do no t have to be refilled as soon as the new shift start s. …

100%1 / 508
5 Tasks on the Machine User Manual SIPLACE CA
5.2 Tasks on the SWS Edition 08/2011 EN
342
5.2.6 Checking and Fitting Tools and Nozzles to the Flip Unit
Switch off the placement machine and the SWS properly.
Open the protective cover above the SWS.
5
Fig. 5.2 - 5 Flip unit with nozzles and reject bins
Legend
5
Check the state and type of the nozzles and tools on the flip unit. If necessary, replace them
with new ones or those appropriate for the product.
You can either use the standard nozzles of the SIPLACE placement machines or rubber tips
together with an appropriate adapter.
Proceed with checking the reject bins.
5.2.7 Checking the Reject Bins of the Flip Unit
Check and empty the reject bins of the flip unit (item 2 in fig. 5.2 - 5).
When replacing the reject bins make sure that the underlying surface is clean and that the bin
is seated correctly in its fixation. Otherwise they are not recognized by the sensors.
Close the protective cover above the SWS.
Switch the SWS and the placement machine on.
(1) Nozzle segment 1 (2) Nozzle segment 2
(3) Reject bin
2
3
3
1
User Manual SIPLACE CA 5 Tasks on the Machine
Edition 08/2011 EN 5.3 Changing Shifts
343
5.3 Changing Shifts
Splice the tapes early. The feeder modules do not have to be refilled as soon as the new shift
starts. This minimizes extended down times.
At the shift change, pass important information on to the next operator. This includes, for in-
stance, changes to the placement program. Perform the steps described in the list in section
5.8
.
Carry out a setup check.
Make sure that the feeder modules are equipped with the correct components, that they are
at the correct locations in the component trolley and that the conveyor increment is set cor-
rectly.
SWS:
Check if the tools are seated correctly at the flip head (see section 5.2.6 on page 342) and at
the die attach head.Where needed, remove any components from the machine. Check if the
correct multi needle kit is inserted (see section 5.2.5 on page 338). Remove flux from the LDU
(if present) and clean the LDU thoroughly with alcohol using the clean cycle. Refer to the user
manual of the -SIPLACE LDU-X for further details (item no. of the German edition [00196057-
xx]).
NOTE
Hand over the line in the same state that you would want to find it in when starting your shift.
This means that: 5
The reject bins of placement machine and SWS are emptied (see section 5.2.7 on page
342) .
The waste tape containers are empty.
The feeding areas are carefully cleaned with a vacuum cleaner.
5 Tasks on the Machine User Manual SIPLACE CA
5.4 Performing Inspections Edition 08/2011 EN
344
5.4 Performing Inspections
5.4.1 Checking the Feeders (X Series)
5
Fig. 5.4 - 1 Checking the X feeder modules
(1) Flap
(2) Blade
(3) Status display
(4) LCD display
5
Check to see whether the tape foil removal container for the X tape feeder module is full.
Open the flap (item 1). Pull out the cover foil and cut it with scissors or on the integral blade