4 Setting up and commissioning Instruction manual SIPLACE SX1/SX 2 Edition V2 and V3 4.6 Commissioning the placement m achine From software version SC .713.1 Edition 12/2020 226 4 Fig. 4.6 - 2 Service tools => automat…

100%1 / 366
Instruction manual SIPLACE SX1/SX2 Edition V2 and V3 4 Setting up and commissioning
From software version SC.713.1 Edition 12/2020 4.6 Commissioning the placement machine
225
4.6.1.1 Performing initial calibration
Click on "Service Tools" in the toolbar.
Click on the Automatic calibration button.
4
Fig. 4.6 - 1 Service tools => automatic calibration
Select Selection => Gantry axis calibration (1).
(1)
4 Setting up and commissioning Instruction manual SIPLACE SX1/SX2 Edition V2 and V3
4.6 Commissioning the placement machine From software version SC.713.1 Edition 12/2020
226
4
Fig. 4.6 - 2 Service tools => automatic calibration => calibrating the gantry axes
The following calibration steps are enabled:
1. Travel range
3. System identification
4. Parameterization X axis
Click on Next (1).
The calibration must be completed without errors.
(1)
Instruction manual SIPLACE SX1/SX2 Edition V2 and V3 4 Setting up and commissioning
From software version SC.713.1 Edition 12/2020 4.6 Commissioning the placement machine
227
4.6.2 Instructing the customer's personnel
Explain all customer-specific installed options, in particular software / software compatibility.
Explain the programming of SIPLACE Pro editors.
Instruct the operators and line engineers in using the station software.
Explain about password protection.
Instruct the customer's personnel according to the instruction manual and the preventive
maintenance.
4.6.3 A test run or starting production
Test the line using the test PCB or a PCB provided by the customer.
Record the customer product and performance data, prepare the data and document the data
in the installation report.
Secure the data and give the customer security copies.