Chapter3. Installation & Operation
When installing the machine newly, observe the following procedure.
Warning Installation or startup by an inexperienced operator may
damage the machine or cause injury. The installation or
startup operation must be performed by our designated C/S
personnel.
3.1. Machine Installation
3.1.1. Unloading Machine
3.1.1.1. Required Tools
Forklift
Safety fence
3.1.1.2. Unloading Procedure
1) Personnel in charge of installation and commissioning must check details of shipment
with the Production Management Department and inform the customer of the expected
arrival time before leaving for the installation site.
2) After arriving at the site, perform visual inspection of the exterior of the machine
before unloading it. (check for crushing of the box, etc.)
3) Check safety related items before unloading the machine. Perform safety measures by
installing safety fence, etc., if necessary. (Example: working in a high location.)
4) The personnel of the Business Department shall receive the delivery certificate and
forms from the operator and check the state and quantity of the machines before
signing the delivery forms and then finishes the machine delivery and acceptance
procedure with the operator.
5) When unloading the machine, provide instructions so that the machine is not damaged
by forklift and ensure the subcontractors responsible for unloading and transportation
understand the precautions to be observed when handling weak parts of the machine.
Then unload the machine using the corresponding jigs and devices. Unload the
machine only by using a forklift.
3.1.2. Unpacking Transportation
3.1.2.1. Required Tools
Forklift and hand lift