semi合集-English.pdf - 第3750页

SEMI F3-94 © SEMI 1990, 2003 5 A1-4.8 Sub-assemblies, after completion, shall be purged and co vered for subsequent installat ion in the field. A1-4.9 A bac king shield (purge t hrough the weld hea d) is required during …

100%1 / 7923
SEMI F3-94 © SEMI 1990, 2003 4
APPENDIX 1
SAMPLE WELDING
SPECIFICATION
NOTE: This related information is not an official part of this
SEMI guide and is not intended to modify or supercede the
official guide. It has been derived from industry
specifications. Publication was authorized by full letter ballot
procedures. Determination of the suitability of the material is
solely the responsibility of the user.
A1-1 General
A1-1.1 The entire piping system will be kept under a
continuous purge until all welding is complete.
A1-1.2 All tools and fixtures used for the assembly and
welding shall be maintained clean and shall not be
removed for use outside of the Class 100 preparation
area.
A1-2 Tubing Preparation Requirements
A1-2.1 Use only tools and handling techniques that
will not mar, disturb the shape of, or in any way reduce
the quality of the materials used in this system.
A1-2.2 Tubing must be under inert gas purge during
the cutting and end-facing/truing operation.
A1-2.3 Tube ends shall be covered while the purge is
removed using a technique that will minimize the
amount of infiltration or contamination. Covers shall be
of non-particulating material.
A1-2.4 Cut ends shall be de-burred and faced to be
square to an appropriate tolerance, per orbital welding
equipment manufacturer’s recommendation. The tubing
shall not be scratched during de-burring. Abrasive
wheels shall not be used. A lathe, milling, or portable
end prep tool that clamps to the exterior of the tube is
permitted.
A1-2.5 Make all necessary preparations for installing
tubing and tube sub-assemblies so that exposure of the
interior surface to atmosphere is minimized.
A1-2.6 Tubing and tube sub-assemblies shall be
mechanically fitted into place, dimensionally verified,
clearances verified, welding parameters set, and all pre-
weld procedures completed in readiness to begin the
welding process prior to removing protective covers.
A1-3 Welding Process Requirements
A1-3.1 Welding shall be by the gas tungsten arc
welding (GTAW) process with backing shielding and
inside tubing purge. All stainless steel tubes shall be
joined using an automatic orbital butt-welding machine.
A1-3.2 During welding, all gas lines must be
continuously purged.
A1-3.2.1 Stainless steel tubing purge lines shall be
used. Flow measurement and control shall be with a
clean rotameter.
A1-3.2.2 Weld shield purge gas shall be filtered with a
0.01 µ m filter connected to the inlet bulkhead fitting of
the welder.
A1-3.3 Every weld shall be tagged, logged, and
inspected.
A1-3.3.1 A daily log shall be maintained on all welds
and an as-built isometric drawing recording all data
shall be maintained in the welding area.
A1-3.3.2 All welds shall be identified with a code
number and cross-referenced with the isometric
drawings for future evaluation.
A1-3.4 As much welding as is feasible will be
performed in the preparation area in the form of sub-
assemblies.
A1-3.5 Alignment of tubing of nominal size 2" in
diameter and larger for orbital welding shall be by an
external clamping jig where space permits.
A1-3.6 Valves shall be located so as to allow space to
operate the valve after installation at the job site.
A1-4 Welding Procedure Requirements
A1-4.1 All materials, testing of welders, and welding
procedures shall comply with the requirements of SEMI
F3.
A1-4.2 Set up the fabrication in a suitable preparation
area or at the job site.
A1-4.3 Make all necessary preparations for installing
tube and tube sub-assemblies such that exposure of the
interior surface to atmosphere is minimized. Insure that
there is purge flow prior to welding.
A1-4.4 On tubes larger than a nominal size of 1/2" ,
place a reducing cap on the discharge end of the tube
with a 12-mm (0.5" ) or smaller outlet.
A1-4.5 Insert the tube ends into the orbital tube weld
holder for butt-welding.
A1-4.6 Perform only one weld joint at a time.
A1-4.7 The completed sections of the piping system
should never be without positive purge pressure and
flow to all system extremities. System extremities
should not be capped in such a way as to permit purge
flow to stop. This purge must be maintained at all
times, including overnight and during weekends and
breaks.
SEMI F3-94 © SEMI 1990, 2003 5
A1-4.8 Sub-assemblies, after completion, shall be
purged and covered for subsequent installation in the
field.
A1-4.9 A backing shield (purge through the weld head)
is required during welding.
A1-4.10 Where a weld is found defective, the
preceding two welds should be tested as described in
Paragraph 7.3.2 of SEMI F3. If either of these welds
shows signs of poor penetration, joint contamination,
lack of joint soundness, surface oxidation,
discoloration, pitting, cracking, defects of fit-up, or
defects of workmanship, then all welds made since the
last welding procedure was established should be
removed and replaced.
A1-4.11 On-site work sample welds shall be made
before each series of welding operations. On-site
sample welds shall also be made at the start of each
workday and any time any welding parameter is
changed.
A1-4.12 Sample test welds shall be made periodically.
These tests shall be compared to the on-site work
sample. Deviation from the on-site work sample shall
be cause for rejection. The sample test welds shall be
made at/when:
1. The beginning of each shift.
2. The end of each shift.
3. Any change in welding procedure, materials, tubing
size, equipment, or equipment adjustments are
made.
4. Any time a concern or deviation to the weld quality
has occurred.
A1-4.13 If the system becomes contaminated due to a
fabrication technique, the contaminated sections shall
be re-cleaned.
A1-4.14 Welding at the job site shall be enclosed in a
clean work area.
A1-4.15 When the welding is performed in a clean
envelope, the envelope shall have openings for the tube
to extend in two directions, a clean polyester film
window, and openings for the hands. HEPA-filtered air
shall be supplied to the envelope under pressure to
ensure a clean working environment.
A1-4.16 The envelope shall be installed prior to
removal of the tube caps. Full purge through the tube to
be welded shall be completed before removing the
clean envelope to attach the weld head.
A1-4.17 Final positioning of the weld head and weld
process shall be performed within the clean envelope.
SEMI F3-94 © SEMI 1990, 2003 6
APPENDIX 2
HEXAVALENT CHROMIUM
ALERT
NOTE: This related information is not an official part of this
SEMI guide and is not intended to modify or supercede the
official guide. It has been derived from the cited document.
Publication was authorized by full letter ballot procedures.
Determination of the suitability of the material is solely the
responsibility of the user.
A2-1 General
A2-1.1 Hexavalent chromium, which is given off when
stainless steel is welded, causes lung cancer in humans.
For information about hexavalent chromium, refer to
HESIS Hazard Alert, June 1992, Hazard Evaluation
System & Information Service, California Occupational
Health Program, 2151 Berkeley Way, Annex 11, Third
Floor, Berkeley, CA 94704.
NOTICE: These standards do not purport to address
safety issues, if any, associated with their use. It is the
responsibility of the user of these standards to establish
appropriate safety and health practices and determine
the applicability of regulatory limitations prior to use.
SEMI makes no warranties or representations as to the
suitability of the standards set forth herein for any
particular application. The determination of the
suitability of the standard is solely the responsibility of
the user. Users are cautioned to refer to manufacturer’s
instructions, product labels, product data sheets, and
other relevant literature respecting any materials
mentioned herein. These standards are subject to
change without notice.
The user’s attention is called to the possibility that
compliance with this standard may require use of
copyrighted material or of an invention covered by
patent rights. By publication of this standard, SEMI
takes no position respecting the validity of any patent
rights or copyrights asserted in connection with any
item mentioned in this standard. Users of this standard
are expressly advised that determination of any such
patent rights or copyrights, and the risk of infringement
of such rights, are entirely their own responsibility.
Copyright by SEMI® (Semiconductor Equipment and Materials
International), 3081 Zanker Road, San Jose, CA 95134. Reproductio
of the contents in whole or in part is forbidden without express writte
n
consent of SEMI.