semi合集-English.pdf - 第6453页
SEMI G76-0299 © SEMI 1999 9 bridge is bala nced, and C 0 is the electrostatic capacity where ε r = 1 calculated from the main electrode area and sample thickness according to the following formula): t r C 6 . 3 2 0 = (b)…

SEMI G76-0299 © SEMI 1999 8
perform the same measurement as in
Section 8.6.3, (3)(a).
(c) High Temperature, High Humidity, Under
Bias After keeping the sample under
85 ± 5°C and 85 ± 5% R.H. for 24 ± 4
hours, apply direct voltage of 100 ± 5V
and perform the same measurement as in
Section 8.6.3, (3)(a). After this, follow the
methods and conditions defined by the
receiving parties.
8.6.4 Inter-Layer Voltage Resistance
(1) Equipment Use the equipment which
conforms to JIS C-2110, Section 6.2 or
similar.
(2) Material Use the same material prepared by
the same method as in Section 8.6.1, (2).
(3) Measurement To measure in normal
conditions, perform the following steps: Using
DC voltage, or a sine wave AC with 50 or 60
Hz frequency, apply 500V to the sample.
Increase the applied voltage up to the defined
voltage over 5 seconds, maintain it for 1
minute and determine whether there has been
any mechanical damage, flash-over, spark-
over, insulation breakdown or other
abnormality.
8.6.5 Relative Permittivity and Dielectric Dissipation
Factor
(1) Equipment
(a) Power Source (see Figure 4 - S) Use a
source which can emit a frequency of 1
MHz, has a sine wave with less than 5%
distortion factor, can give a stable flow of
the define voltage to the sample, and have
electro-static and magnetic shielding to
prevent direct coupling between the power
source and bridge.
(b) Shielded Transformer (see Figure 4 - T
1
)
Use a transformer with which the
power source internal impedance and the
bridge impedance can be adjusted, and
one where the winding on the bridge
inside the transformer is shielded with a
grounded conductor.
(c) Ratio Arm (see Figure 4 - T
2
) Use a
ratio arm with a winding ratio of 1:1
(tolerance of less than 0.2%). Make a non-
inductive connection of the primary
winding and secondary winding of a
transformer with as little leakage
inductance and winding resistance.
Ground the connection point as shown in
Figure 4 - e, and connect the other 2
terminals to l and r to make it unbalanced.
(d) Variable Capacitor (see Figure 4 - Cs
1
,
Cs
2
) Use two air capacitors with guards
that have a capacity of approximately 200
pF, one being the standard capacitor Cs
1
and the other being the measuring
capacitor Cs
2
, and insert parallel with the
sample Cx.
(e) Conductance Shifter (see Figure 4 - g)
Insert a resistor with a constant
conductance in between m and d in Figure
4, where the resistance between l and m
can be changed between 100–0 Ω, and the
resistance between m and r can be
changed between 100–200 Ω.
(f) Balance Detector (see Figure 4 - g) Use
a balance detector which responds only to
the power source voltage base plate used
in the bridge.
(2) Material Prepare the samples according to
the method described in Section 8.6.1, (3). Use
Figure 3 for the shape of the electrode.
(3) Measurement Use the following to measure
under normal conditions: Measure the
thickness of the samples in units of 1 µm, and
measure the inner diameter of the gap in the
circular upper electrode in units of 0.05 mm.
Also, confirm that the circular gap between the
main electrode and the guard electrode is 1 ±
0.1 mm. Connect the sample at position Cx,
and by adjusting the measuring capacitor Cs
2
and the conductance shifter, with the bridge
balanced, measure the standard capacitor Cs
1
value and the measuring capacitor Cs
2
value,
the resistance value between conductance
shifter m and d, and the resistance value
between m and r. The measuring frequency is
1 MHz.
(4) Calculation Use the equation below.
(a) Relative Permittivity
)(
0
Ω=
C
Cx
r
ε
Where Cx is the difference in the
capacitance values of standard capacitor Cs
1
and measuring capacitor Cs
2
(when the

SEMI G76-0299 © SEMI 1999 9
bridge is balanced, and C
0
is the electrostatic
capacity where εr = 1 calculated from the
main electrode area and sample thickness
according to the following formula):
t
r
C
6.3
2
0
=
(b) Dielectric Dissipation Factor
fCx
Gx
π
δ
2
tan =
100
S
GGx ×=
Where Gx is the sample conductance, G is
the conductance between m and d, S is the
resistance value between m and r, S/100 is
the resistance factor, f is the measuring
frequency, and π is pi.
Figure 4
Measurement Circuit for Relative Permittivity and
Dielectric Dissipation Factor
8.7 Other Tests
8.7.1 Heat Resistance
(1) Equipment
(a) Solder Use Standard H60A or H63A
under JIS Z-3282.
(b) Solder Bath A vessel with a depth of
more than 50 mm to hold the solder at
between 200–300°C and can be adjusted
± 3°C.
(1) Material Using the TCP polyimide adhesive
tape as received from the vendor, laminate and
cure it according to the method described in
Section 8.2. Cut into 25 mm squares for
samples.
(2) Preparation Keep in 105 ± 5°C oven for 1
hour.
(3) Test After preparation, quickly place in 260
± 5°C solder bath and let float for 5
+ 1
-0
seconds.
Perform visual check for swelling.
8.7.2 Water Absorption Test
(1) Equipment
(a) Scale Use a scale that can measure in
1 mg units.
(b) Vessel Use a vessel in which the
samples can be totally immersed.
(c) Dessicator Use a dessicator which
allows samples heated to 80°C to cool
off.
(1) Material Using the TCP polyimide
adhesive tape as received from the vendor,
laminate and cure it according to the method
described in Section 8.2. In addition, remove
all copper foil by etching, and dry for 30
minutes at 80 ± 5°C. Cool in the dessicator,
and use samples cut into length 500 ± 5 mm,
and width 20 ± 1 mm. Depending on the
shape of the vessel to be used for
immersion, it is feasible to several pieces of
a suitable length.
(2) Test Weigh the sample in increments of 1
mg. Place sample in 23 ± 2°C distilled water.
After 24 ± 1 hours, wipe off water and
measure sample again in increments of 1 mg.
(3) Calculation Use the following formula:
(%)100
2
12
×
−
W
WW
Where W
1
and W
2
are the weight before and
after immersion respectively.
8.7.3 Heat Shrinkage Use the standard value of the
base film and the various values for measuring
conditions.
(1) Equipment Use a measuring device with
optical equipment which can read with at
least 5/100,000 (0.005%) precision.
(2) Material Mark three places along the
width on a sample with size larger than 50
mm square.

SEMI G76-0299 © SEMI 1999 10
(3) Preparation Place for more than 1 hour in
a managed environment of room
temperature ± 2°C, ± 5% R.H.
(4) Measuring Method Before Heating
Measure the distance between the marks
with the equipment (1) on a sample that has
been prepared according to (3) above.
(5) Heating Keep the samples in an oven at
200 ± 3°C for more than an hour, making
sure that it is not effected from the outside.
(6) After-Processing Leave sample for more
than 1 hour in the conditions described in (3)
above.
(7) Measuring Method After Heating Use the
same method as (4) above.
(8) Calculation Use the following formula,
where L
1
is the dimension from (4), and L
2
is the dimension from (7):
(%)100
1
21
×
−
L
LL
8.7.4 Coefficient of Thermal Expansion Use the
standard value of the base film and the various values
for measuring conditions.
(1) Equipment Use TMA equipment.
(2) Material Prepare sample with width of 3
mm and length of more than 15 mm.
(3) Preparation To remove the effects of
thermal shrinkage and moisture, heat at
more than 300°C for 30 minutes.
(4) Measuring Method With a sample that has
been prepared according to (3) above,
measure the stretching in the sample on a
TMA, in the range between room
temperature and 300°C, raising the
temperature at less than 20°C/min.
(5) Calculation Use the following formula,
reading a gradient from an arbitrary scope,
within the area between room temperature
and 200°C (i.e., 50−200°C, 100−200°C):
)(
6
100
)
01
(
0
01
ppm
TTL
LL
×
−
−
Where T
0
and T
1
are the temperatures in the
area for Linear Expansion, L
0
is the length
of the sample at T
0
(°C) and L
1
is the length
of the sample at T
1
(°C).
8.7.5 Tensile Strength, Elongation Use the standard
value of the base film and the various values for
measuring conditions.
(1) Equipment Use a pull strength meter and
recorder.
(2) Material Use samples with a width of
more than 10 mm and length of
approximately 200 mm. The samples should
be 3 pieces taken from the beginning,
middle and end of the roll.
(3) Measuring Method After measuring the
width of the sample, fix it in the pull
strength meter. Use a clamping distance of
approximately 100 mm to test pull strength.
Measure the pull load and stretch at point of
breakage.
(4) Calculation After measuring the pull
strength and elasticity of each sample,
calculate the average of each.
8.7.6 Flammability
(1) Equipment
(a) Sample box or draft chamber which can
maintain calm conditions.
(b) Test stand and clamp.
(c) Bunsen burner with pipe length of
approximately 100 mm, aperture
diameter of 9.5 ± 0.5 mm, using methane
gas or natural gas with a heat generation
volume of approximately 37 MJ/m
3
.
(d) Stop-watch or timer.
(e) Sheet of absorbent cotton 50 mm square
with a maximum natural thickness of 6.4
mm.
(f) A dessicator with dehydrated hydrated
calcium.
(g) A test oven which can maintain a
temperature of 23 ± 2°C and R.H. of 50
± 5%.
(h) A test oven which can maintain a
temperature of 70 ± 1°C.
(i) A pole with a diameter of 13 ± 5 mm.
(2) Material Using the TCP polyimide
adhesive tape as received from the vendor,
laminate and cure it according to the method
described in Section 8.2. In addition, remove
all copper foil by etching, and dry for 30
minutes at 80 ± 5°C. As shown in Figure 5,