SEMI S20-0303 © SEMI 2003 1 SEMI S20-0303 SAFETY GUIDELINE FOR IDEN TIFICATI ON AND DOCUMENTATION OF ENERGY ISOLATION DEVI CES FOR HAZARDOUS ENERGY CONTROL This safety guideline was techni cal ly approved by the Environm…

SEMI S19-1102 © SEMI 2002 6
10.2 Records
10.2.1 Course records should identify
• The target audience and stated learning
objective(s),
• Sources, materials and references used for training
development,
• Persons designing and developing the training and
their qualifications,
• Training materials developed for the course,
• Regulations, standards or legislation for which the
training is intended to comply,
• Methods for demonstrating competency, and
• Plans for evaluation and continuous improvement
of the course.
10.2.2 Delivery records for each training event should
identify:
• Name and description of the course,
• Date, location, and duration of the training,
• Name, identification number and employer of
students participating in the training,
• Person(s) delivering the training,
• Students successfully completing the training and
completion date (if training event spanned multiple
days),
• Competency demonstration records, and
• The subject matter presented.
10.2.3 Trainer records should include the name,
qualifications, contact information and employer of the
trainer.
10.2.4 Program management records should include
documented periodic evaluations of the training
program and reevaluations of courses.
10.3 Record Confidentiality and Availability
10.3.1 Records should be maintained such that they
meet applicable requirements for availability,
disclosure, confidentiality, and protection of trade
secrets.
10.3.2 The employer should ensure the student is
provided confirmation of successful training
completion within a reasonable time.
10.3.3 If the facility owner is different than the
employer, documentation of training completion and
contact for verification upon request should be made
available to the facility owner in a language acceptable
to the facility owner. Records, such as those identified
within this guideline, are considered documentation that
could be used for verification.
10.3.3.1 Suggested methods of providing
documentation of training completion in the field
include:
• A training passport that summarizes training
received with course completion acknowledged by
the instructor with signature, and
• Training certification cards that identify the
courses and completion dates of training received.
10.3.3.2 When an individual holding a valid training
certification issued by his/her previous employer
changes employers, it is suggested that the new
employer upon verification of the validity of the
training “certification” and associated curriculum, re-
certify its new employee by written examination and
practical demonstration to the current training
guidelines.
NOTICE: SEMI makes no warranties or
representations as to the suitability of the guidelines set
forth herein for any particular application. The
determination of the suitability of the standard is solely
the responsibility of the user. Users are cautioned to
refer to manufacturer' s instructions, product labels,
product data sheets, and other relevant literature,
respecting any materials or equipment mentioned
herein. These standards are subject to change without
notice.
By publication of this guideline, Semiconductor
Equipment and Materials International (SEMI) takes no
position respecting the validity of any patent rights or
copyrights asserted in connection with any item
mentioned in this guideline. Users of this guideline are
expressly advised that determination of any such patent
rights or copyrights, and the risk of infringement of
such rights are entirely their own responsibility.
Copyright by SEMI® (Semiconductor Equipment and Materials
International), 3081 Zanker Road, San Jose, CA 95134. Reproduction o
f
the contents in whole or in part is forbidden without express written
consent of SEMI.

SEMI S20-0303 © SEMI 2003 1
SEMI S20-0303
SAFETY GUIDELINE FOR IDENTIFICATION AND DOCUMENTATION
OF ENERGY ISOLATION DEVICES FOR HAZARDOUS ENERGY
CONTROL
This safety guideline was technically approved by the Environmental, Health, and Safety Committee and is
the direct responsibility of the North American Environmental, Health, and Safety Committee. Current
edition approved by the North American Regional Standards Committee on November 22, 2002. Initially
available at www.semi.org January 2003; to be published March 2003.
NOTICE: Paragraphs entitled “NOTE” are not an
official part of this document and are not intended to
modify or supersede the official guideline. The task
force has supplied them to clarify and to enhance usage
of the guideline by equipment designers.
NOTICE: The intent of the task force that produced
this document is that conformance to the “should”
provisions of this guideline comprises conformance
with this guideline.
1 Purpose
1.1 This guideline is intended to establish a method for
the unique identification of energy isolation devices
(EID) used for lockout/tagout (LOTO). This
identification is intended to occur both at the devices
and at those places in the supplier-provided manuals
where the devices are referenced in tasks or procedures.
NOTE 1: Throughout this document, “LOTO EID” refers to
these devices.
1.2 This document supplements the existing provisions
in SEMI S2 (for Hazardous Energy Isolation) and
SEMI S13 (for providing appropriate documentation)
with a uniform graphical representation and
identification system.
1.3 This document also provides guidance for
developing instructions for operating LOTO EIDs.
2 Scope
2.1 This guideline applies to equipment used to
manufacture, measure, assemble, and test
semiconductor products, and the maintenance and
service procedures associated with the equipment.
2.2 This guideline provides criteria for documentation
and identification of all supplier-specified LOTO EIDs
meeting the criteria of SEMI S2. This includes
isolation devices that the supplier intends to be
provided by the end user.
EXCEPTION: Equipment in which a cord and plug
connection is the only LOTO EID is exempt from this
guideline.
NOTE 2: Isolation devices with locking capability are not
necessarily LOTO EIDs, unless the supplier specifies them as
LOTO EIDs.
NOTE 3: In some jurisdictions, it is the responsibility of the
supplier to specify the energy isolation points that must be
locked out in conjunction with the manufacturer-specified
maintenance procedures. However, the end user is
responsible for the overall hazardous energy control program
for the work site and for the installation of additionally
required facility EIDs. The user is not responsible for EIDs
that are required by regulation to be incorporated within the
equipment.
NOTICE: This safety guideline does not purport to
address all of the safety issues associated with its use.
It is the responsibility of the users of this safety
guideline to establish appropriate safety and health
practices and determine the applicability of regulatory
or other limitations prior to use.
3 Limitations
3.1 This document is not intended to provide
guidelines for developing or replacing user-site energy
isolation programs.
3.2 This document is not intended to be used in place
of the need for adequate training of individuals who
perform hazardous energy control.
3.3 This document is not intended to conflict with laws
and regulations on Control of Hazardous Energy.
3.4 This guideline does not contain criteria or
requirements for providing a particular LOTO EID to
be used in a LOTO program.
NOTE 4: The requirements and criteria for providing a
particular LOTO EID for use in a LOTO program may be
found explicitly or implicitly in SEMI S2, equipment design
standards, United States OSHA requirements, or in various
good engineering practices.
3.5 This document is not intended to replace or
supersede SEMI S2 or any other SEMI Safety
Guideline.
3.6 This document is not intended to be applied
retroactively, i.e., to designs already in the field.

SEMI S20-0303 © SEMI 2003 2
3.7 This document does not apply to the labeling of
hazards, which is the function of SEMI S1.
4 Referenced Standards
4.1 SEMI Standards
SEMI S1 Safety Guideline for Equipment Safety
Labels
SEMI S2 Environmental, Health, and Safety
Guideline for Semiconductor Manufacturing Equipment
SEMI S8 Safety Guidelines for Ergonomics
Engineering of Semiconductor Manufacturing
Equipment
SEMI S13 Safety Guidelines for Operation and
Maintenance Manuals Used With Semiconductor
Manufacturing Equipment
4.2 ANSI Standards
1
ANSI Z535.1 Color Coding for Labels
4.3 Code of Federal Regulations - United States of
America
2
29 CFR 1910.147 The Control of Hazardous Energy
(lockout/tagout)
29 CFR 1910.147
Appendix A “Typical Minimal
Lockout Procedure”
4.4 ISO Standards
3
ISO 3864 Safety Colours and Safety Signs
NOTICE: Unless otherwise indicated, all documents
cited shall be the latest published versions.
5 Terminology
5.1 Abbrevitions and Accronyms
5.1.1 LOTO acronym for lockout/tagout.
NOTE 5: Also equivalent to the term Hazardous Energy
Isolation (HEI), which may be used in some jurisdictions.
5.2 Definitions
5.2.1 blocking (v) preventing flow of material as
through piping or preventing energies (such as
1 American National Standards Institute, New York Office: 11 West
42nd Street, New York, NY 10036, USA. Telephone: 212.642.4900;
Fax: 212.398.0023 Website: www.ansi.org
2 Available from Occupational Safety and Health Administration,
U.S. Department of Labor, http://www.osha.gov
3 International Organization for Standardization, ISO Central
Secretariat, 1, rue de Varembé, Case postale 56, CH-1211 Geneva 20,
Switzerland. Telephone: 41.22.749.01.11; Fax: 41.22.733.34.30
Website: www.iso.ch
suspended weights or springs) held in a suspended state
from movement.
5.2.2 clean room compatible materials — materials
approved for use within a fabrication facility, including:
laminated card stock or paper, clean room paper,
electronic media or other approved media.
5.2.3 Energy Isolation Device (EID) a mechanical
device that physically prevents the transmission or
release of energy, including but not limited to the
following: a manually operated electrical circuit
breaker; a disconnect switch; a manually operated
switch by which the conductors of a circuit can be
disconnected from all ungrounded supply conductors,
and, in addition, no pole can be operated independently;
a line valve; a block; and any similar device used to
block or isolate energy. Push buttons, selector
switches, and other control devices are not energy
isolation devices. [OSHA 29 CFR 1910.147]
NOTE 6: Lockout devices (elsewhere defined in this
document) are not energy isolation devices.
5.2.4 graphical using an image or multiple image
representation that reflects the equipment as assembled
and is used for indicating the location of the individual
LOTO EIDs in relation to the equipment being
maintained. Images include labeled drawings, or
photographs enhanced with labels.
5.2.5 graphical reference guide — the merger of text
instructions and graphical representations of the
equipment in a manner that provides a clear description
of the task and a simple means of locating the correct
devices.
5.2.6 lockout the placement of a lockout device on
an energy isolation device, in accordance with an
established procedure, ensuring that the energy
isolation device and the equipment being controlled
cannot be operated until the lockout device is removed.
[OSHA 29 CFR 1910.147]
5.2.7 lockout device a lock and associated hardware
used to secure an EID in the safe position and prevent
energy flow.
NOTE 7: Energy isolation devices (elsewhere defined in this
document) are not lockout devices.
5.2.8 maintenance planned or unplanned activities
intended to keep equipment in good working order.
(See also definition for service.) [SEMI S2]
5.2.9 marked — identified by the use of a label,
engraving, silk screening, etching, or other physical and
durable indication; placed near components or on
systems for the purpose of matching to identifying
documentation.