semi合集-English.pdf - 第4066页

SEMI F55-0600 © SEMI 2000 4 NOTE 6: Data throughout this test m ay be recorde d in a forma t si mila r to that foun d in Table A 1.1. 13.6 Open valve V1 and flow dry N 2 a t a setpoint of 80% ± 5% of the DUT FS an d wait…

100%1 / 7923
SEMI F55-0600 © SEMI 20003
10.2 Become familiar with the safe handling practices
associated with the corrosive gas before undertaking
this test.
11 Preparation of Apparatus
11.1 The test apparatus is the source of three gases—
dry N
2
, dry HCl, and N
2
containing a known level of
water vapor. Each gas can be valved through the DUT
individually with minimal cross contamination. The
DUT actively controls the gas flow in each case. The
gas then flows into either a scrubbed exhaust system for
safe disposal or a reclamation system. A reference
flowmeter in the dry N
2
supply line is used to detect
changes in calibration of the DUT when dry N
2
is
flowing in series through both devices.
11.2 Setup and Schematic — See Figure 1 for a
schematic of the test apparatus. This schematic may
not show in detail all the components required in an
actual system.
11.3 Supply the manufacturer's reco mmended power
to the DUT. Provide MFC setpoint and purge
command (if available). Monitor the following:
11.3.1 DUT setpoint input.
11.3.2 DUT indicated flow output.
11.3.3 DUT valve drive output (if available)
11.3.4 actual flow (output of reference flowmeter)
11.4 Verify that the proper moisture levels exist in
each of the test gases.
11.5 Provide a purge flow loop that maintains a
constant flow of dry N
2
in the line from the DUT to the
exhaust system. Flow in this loop must be sufficient to
prevent back diffusion into the DUT of moisture
generated in the exhaust system, particularly when flow
into the DUT is shut off for measuring zero.
11.6 If the moisture generator is sup plied from the
same N
2
source that supplies the dry N
2
, take
precautions to avoid the diffusion of moisture from the
moisture generator into the dry N
2
line. Such
precautions may include the use of separate pressure
regulators and other valving.
11.7 Moisture generators typically take time to
stabilize. A continuous flow should be maintained
through the moisture generator during the test to
maintain a stable moisture flow. This may require
diverting the output flow to a vent when not flowing
through the DUT.
11.8 Periodically verify the moisture concentration of
wet N
2
with a suitable moisture analyzer.
11.9 Follow manufacturer set-up procedures for all
equipment.
11.10 Conduct the test at an ambient temperature of 22
± 2°C.
11.11 The DUT moisture generator, flowmeters, and
other instrumentation should have been stabilized at
room temperature for 24 hours before beginning the
tests. It is not necessary to flow gas during this
stabilization time.
11.12 All portions of the plumbing system that could
contain HCl must be helium leak tested per SEMI F1
before introducing HCl into the system. When
changing the DUT or other components, at least those
portions of the system that were changed must be re-
tested.
NOTE 4: Small leaks in a corrosive gas system can become
much larger without warning.
12 Calibration and Standardization
12.1 Calibrate all instrumentation using current
standards that are traceable to an appropriate standards
laboratory. In the absence of appropriate standards, use
manufacturer recommendations for calibration.
13 Procedure
NOTE 5: Refer to Figure 2 for a flowchart of the following
test.
13.1 Set the pressure of each of the HCl and Dry N
2
gas sources at 140 kPa ± 5%. Set the pressure of the
N2 to the moisture generator to the appropriate value
recommended by the manufacturer. If the test must be
run at some other pressure, because of a limitation of
the DUT, report this fact in the test results.
13.2 Start the wet N
2
flow to vent or through the
moisture analyzer. Establish a stable moisture
concentration at 100 ppmv ± 20% before beginning the
test sequence. Set the wet N
2
to flow within ± 5% of
the DUT flow that will be run during the test.
13.3 Place the DUT control valve in the purge or fully
open position by supplying a purge command or a
200% setpoint. Purge with dry N
2
at a rate of one to
two times FS flow for one hour to establish initial
conditions. The purge rate is controlled by adjusting
the supply pressure and is monitored by a purge-rate
flowmeter located in the gas-supply path. Follow the
manufacturer's procedure for fully opening the DUT
control valve.
13.4 Provide a setpoint to the DUT for 80 ± 5% of FS
flow.
13.5 Determining the Test Baseline and Measurement
Repeatability.
SEMI F55-0600 © SEMI 2000 4
NOTE 6: Data throughout this test may be recorded in a
format similar to that found in Table A1.1.
13.6 Open valve V1 and flow dry N
2
at a setpoint of
80% ± 5% of the DUT FS and wait 10 minutes.
13.7 Record:
13.7.1 DUT setpoint
13.7.2 DUT indicated flow
13.7.3 DUT valve drive output (if available)
13.7.4 Actual flow
13.8 Stop flow by closing V1. Drive the MFC control
valve to a closed position by providing a zero setpoint
or as otherwise provided by the manufacturer. Allow
the MFC indicated flow output to stabilize for a
minimum of three minutes.
13.9 Record the DUT indicated flow and the actual
flow during the zero flow condition.
13.10 Repeat Sections 13.6 through 13.9 twelve times.
This will yield 12 data points for each of the six
measured parameters.
13.11 For each of the six parameters recorded,
perform the following calculation on the 12 baseline
data points to determine the repeatability of the
measurement:
(highest value - lowest value) × 100
average of the 12 values
13.12 If each of the six parameters is not repeatable
within 0.2% during these two hours, subsequent test
data may not be valid and the problem should be
resolved before proceeding with the test.
13.13 Baseline
NOTE 7: Use the averaged value of the measurements made
in Section 13.13 for each parameter as the baseline for that
parameter in the following tests.
13.14 Test Sequence — Without changing the DUT
setpoint, repeat the test sequence in Sections 13.19-
13.22 every 30 minutes, continuously, 24 hours per day,
seven days per week until one of the following test
termination conditions is met.
13.15 The test should not be interrupted because the
DUT may continue to corrode during the interruption,
making test results non-repeatable. The output of the
moisture generator should be measured periodically
during the test sequence to ensure that it remains within
the test specifications.
13.16 Terminate the test sequence if:
13.16.1 The DUT fails to function
13.16.2 The actual-flow shift from baseline exceeds
25%
13.16.3 The valve drive exceeds the manufacturer's
limits
13.16.4 The DUT indicated flow differs from
commanded setpoint by > 5%
13.16.5 The test exceeds 5000 cycles
13.17 Flow dry N
2
for five minutes. After five
minutes, record data on the six test parameters as done
in Section 13.7, interrupting flow to record the DUT
indicated flow and reference flowmeter output at zero
flow. After taking measurements, flow dry N
2
again so
that the total length of this step is 10 minutes. Record
data as shown in Figure 3.
13.18 Flow dry HCl for seven minutes.
13.19 Repeat Section 13.19 and then proceed to
Section 13.22.
13.20 Flow wet N
2
for three minutes. If no test
termination condition is met as described in Section
13.18, repeat Sections 13.19 - 13.22. If a test
termination condition is met, proceed to Section 13.23.
13.21 After the test has been completed, place the
DUT control valve in the purge or fully open position.
Purge with dry N
2
for one hour or at least 50 volume
changes. Cycle the purge gas for 15 seconds on and 15
seconds off by opening and closing V1 for the duration
of the purge. Follow the manufacturer's procedure for
fully opening the DUT control valve.
NOTE 8: Verify purge flow with the reference flowmeter or
by using other means. Corrosion may have rendered the
control valve inoperable. An alternate approach for purging
any corrosive material from the system may have to be
followed.
13.22 Alternate Approach to Purging.
13.23 If gas cannot be purged through the DUT, cycle-
purge each end of the DUT separately using Sections
13.26 through 13.28.
13.24 With valves V2 and V3 closed for the duration
of the procedure, close valve V6 and pressurize both
sides of the system by opening V1 and V7 for 15
seconds.
13.25 Vent pressure through the exhaust system by
closing V1 and opening V6 for 15 seconds.
13.26 Repeat pressure and vent cycles for a minimum
of one hour.
13.27 Remove the DUT. Preserve the test system, if
desired, by taking steps to exclude atmospheric
moisture. Such steps could include capping the system
and shutting all valves. Alternately, the DUT may be
SEMI F55-0600 © SEMI 20005
replaced with a spool piece. The system can then be
continuously purged with dry N
2
.
NOTE 9: The DUT will be contaminated with corrosive
material. See Precautions in Section 10. Preserve the DUT
for failure analysis, if desired.
14 Calculations or Interpretation of Results
14.1 Report data in a tabular format and graph per
Appendix 1. Any parameter which changes more than
1% from its baseline should also be graphed. Note the
reason the test was terminated. Test results may be
summarized in a single parameter by reporting the
number of test cycles to reach a 2% shift in actual flow
or to reach DUT failure, whichever occurs first. In this
test, more data is reported than is required to calculate
the gross test result. The extra data is used when
analyzing test results to determine the cause of failure.
Further explanation of the significance of the data is
beyond the scope of this test method.
15 Data Analysis.
15.1 Calculate any parameter-shift in percent as
follows:
(baseline value - current value) × 100
baseline value
16 Reporting Results
16.1 Report the number of test cycles to reach a 2%
shift in actual flow or to reach DUT failure, whichever
occurs first.
17 Precision and Accuracy
17.1 This method is limited in its precision by the
calibration of the measurement devices, the temperature
of the apparatus, and the concentration of water vapor
in N
2
. Sources of bias are unknown at this time, but
they probably include peculiarities in the construction
of the apparatus.
18 Related Documents
18.1 Material safety data sheet (MSDS) for hydrogen
chloride, which can be obtained from a supplier of the
gas.
19 Illustrations
Purge Rate
Flow Meter
MFM
Reference
Meter
DUT
Exhaust
System
Moisture
Generator
MFC
or Control
Valve
Vent
Moisture Level
Test Port
V8
V3
V2
V7
V1
V6
V4
V5
Purge Flow
Dry HCl in
Dry N
2
in
Dry N
2
in
Figure 1
Schematic of Apparatus